Action programme increases ore production

Action programme increases ore production

ID: 176977

(Thomson Reuters ONE) -


Production of iron ore products during 2012 is expected to be approx. 400,000
tonnes, compared with the planned 500,000 tonnes. This is expected to result in
lost revenue of approx. 70 million in 201

The production shortfall is due to the fact that it took longer to fine-tune the
sorting plant than predicted. At the same time, crude ore with low average iron
content has been mined and processed.  Process and equipment deficiencies have
emerged during the fine-tuning of the sorting plant.

Some of these have been addressed, while others will be dealt with in stages
over autumn. The full annual production rate of 1.5 million tonnes of iron ore
products is expected to be achieved during the first half of 2013.

Since the summer, ore deliveries to Dannemora's steel customers have been
running according to the existing supply contracts.

Iron ore prices during the remainder of 2012 and the early part of 2013 are
expected to be slightly lower than the previous assessment, which will also
affect the Company's cash flow.

Together, the revenue shortfall and action programme mean that there is a need
to strengthen the Company's liquidity by approx. SEK 100 million during the
present year. Different financing options are being investigated at present.


Read Press release below

Press release 22 August 2012:
http://hugin.info/137553/R/1635713/525478.pdf



This announcement is distributed by Thomson Reuters on behalf of
Thomson Reuters clients. The owner of this announcement warrants that:
(i) the releases contained herein are protected by copyright and
other applicable laws; and
(ii) they are solely responsible for the content, accuracy and
originality of the information contained therein.

Source: Dannemora Mineral AB via Thomson Reuters ONE
[HUG#1635713]








Unternehmensinformation / Kurzprofil:
drucken  als PDF  an Freund senden  DGAP-News: Viscom AG: Global economic conditions impact figures in the second quarter Ericsson : Ericsson sells its EDA 1500 GPON assets
Bereitgestellt von Benutzer: hugin
Datum: 22.08.2012 - 20:56 Uhr
Sprache: Deutsch
News-ID 176977
Anzahl Zeichen: 2099

contact information:
Town:

Österbybruk



Kategorie:

Business News



Diese Pressemitteilung wurde bisher 199 mal aufgerufen.


Die Pressemitteilung mit dem Titel:
"Action programme increases ore production"
steht unter der journalistisch-redaktionellen Verantwortung von

Dannemora Mineral AB (Nachricht senden)

Beachten Sie bitte die weiteren Informationen zum Haftungsauschluß (gemäß TMG - TeleMedianGesetz) und dem Datenschutz (gemäß der DSGVO).

Dannemora Mineral AB: Press Release 13 November 2009 ...

AGREEMENT SIGNED WITH VOESTALPINE FOR TRIAL DELIVERY OF IRON ORE Dannemora has signed an agreement with Austrian steel company Voestalpine AG for the delivery of approx. 10,000 tonnes of iron ore products. The ore will be shipped from the port of Ha ...

Dannemora Mineral AB: Interim Report January - June 2009 ...

* With global demand for steel having stabilised in the second quarter, many steel companies entered the third quarter in a position to raise their prices. * Iron ore imports to China hit a record high in the first half of 2009, increa ...

Alle Meldungen von Dannemora Mineral AB



 

Werbung



Facebook

Sponsoren

foodir.org The food directory für Deutschland
Informationen für Feinsnacker finden Sie hier.

Firmenverzeichniss

Firmen die firmenpresse für ihre Pressearbeit erfolgreich nutzen
1 2 3 4 5 6 7 8 9 A B C D E F G H I J K L M N O P Q R S T U V W X Y Z