Paladin Energy Ltd: Quarterly Activities Report For Period Ending-31 March 2013

Paladin Energy Ltd: Quarterly Activities Report For Period Ending-31 March 2013

ID: 249871

(firmenpresse) - PERTH, WESTERN AUSTRALIA -- (Marketwired) -- 04/17/13 -- Paladin Energy Ltd ("Paladin" or "the Company") (TSX: PDN)(ASX: PDN) is pleased to provide its Quarterly Activities Report for the three month period ended 31 March 2013.

HIGHLIGHTS

SAFETY

The Company's high safety performance was impacted by two lost time injuries (LTIs) incurred during the period with the 12-month moving average Lost Time Injury Frequency Rate (LTIFR) increased from 1.1 to 1.2. One LTI occurred at Langer Heinrich Mine (LHM) and involved an operator suffering an injury to his back when he slipped and fell approximately 2m. The incident investigation revealed that the employee was not using a safety harness and procedures are being adjusted to mitigate further similar incidents. The other LTI was exploration related and involved a contractor suffering a crushed finger while handling fuel drums at the Michelin camp in Canada.

During the period, the annual NOSA HSE grading audit for LHM confirmed a 4 Platinum Star rating.

There were no LTIs at Kayelekera Mine (KM) for the period. KM also achieved a milestone 365 LTI free days on 28 March 2013.

QUARTERLY URANIUM SALES

Sales for the quarter were 1,920,230lb U3O8 generating revenue of US$106M, representing an average sales price of US$55.22/lb U3O8 (average Ux spot price for the quarter was US$42.71/lb U3O8). As foreshadowed in the last Quarterly Report, sales are now more closely aligned with production although some variations can be expected from quarter-to-quarter due to customer requirements.

LANGER HEINRICH MINE, Namibia (100%)

Production by quarter

Production totalled 1,230,081lb U3O8, which was 13% lower than the previous quarter. The plant continued to perform well and in accordance with the design parameters of the Stage 3 upgrade, which was designed around the limitations of the NamWater infrastructure that supplies water to the mine. Consequently, any disruption to the supply of water has a direct impact on production and during the quarter the supply was disrupted as NamWater acted to upgrade its supply infrastructure in the region to accommodate the additional water requirements associated with new mining developments (mainly the new Husab uranium mine).





This action is part of a long-standing initiative by NamWater to transition from aquifer water to desalinated water later in the year.

In order to overcome the current water supply constraint on production, an interim agreement is being concluded with NamWater and Areva, the owners of the desalination plant in Namibia, to access additional desalinated water, ahead of schedule, from May 2013. In addition to this, an increased focus on water conservation at site will mitigate against further disruptions.

This combined strategy of a short-term agreement and water conservation measures will eliminate any further disruptions to the water supply in the interim and thus allow a resumption of nameplate or better production.

Mining

The overall mined quantities decreased as planned over the quarter. The mining schedule was previously revised as part of the cost rationalisation programme. Ore mining and availability remained unaffected.

Mining continued in three pits with sufficient ore exposed to fulfil plant feed requirements.

ROM ore stocks have been maintained at around four weeks' supply while being supplemented by medium grade ores in line with the crusher blend requirements.

Process Plant

The plant experienced reduced throughput in the March quarter as reflected below:

Ore feed tonnage through the process plant reduced by 12.8% with total throughput of 797,696t. The reduced throughput can be attributed to the temporary water constraints and some operational issues mainly in ion exchange. These issues have since been rectified. The water constraints, which influenced the general performance capability of the plant, were the most significant.

The scrub efficiency reduced to 91.1% (against a design of 93%). As reported previously, optimisation work in the screening area in order to further improve performance is ongoing, with the classification section remaining the focal area of these optimisation efforts.

The extraction in the leaching circuit continued to improve in line with expectations with a new quarterly record recovery of 95.8%. This improved performance is due to improved heat management and subsequent consistently higher leach temperatures as well as the previously reported initiatives on improving throughput consistency.

The efficiencies in the Counter-Current Decantation (CCD) circuit have improved as a result of the continuing optimisation efforts in this circuit. These improvements have had a further benefit of reducing overall water consumption and, as a consequence, reagent consumption leading to sustainable reductions in C1 operating costs. Further modifications and improved operating procedures are being implemented, which should lead to additional improvements.

The overall plant recovery reduced slightly to 86.7%. The most significant contributors were a result of lower scrub efficiency, lower ion exchange ("IX") efficiency and a reduction in the return solution from the tailings storage facility. The leach section achieved record recovery whilst the wash efficiency also showed a marked improvement from the previous quarter.

Construction work on the newest tailings storage facility ("TSF3") (full in-pit tailing deposition area) continued during this period and is scheduled for completion in the December quarter. It is now envisaged that the tailings deposition to TSF2 will extend to the second half of CY2013. Construction of TSF2 extension also continued throughout the quarter.

Production Optimisation

Optimisation of the process continued during the quarter with material and sustainable gains being achieved:

The installation of the Hydrosort classification unit remains on track for commissioning early in the September quarter and is expected to improve front end ore beneficiation in the coming year.

Further optimisation targets are also being developed on the basis of expanded Stage 3 operating experience.

KAYELEKERA MINE, Malawi (85%)

Production by quarter

In the March quarter, total production fell slightly to 761,992lb; however, average daily production increased marginally to 8,467lb/day compared with 8,395lb/day during the December 2012 quarter.

Mining

Mining data

Total material mined for the quarter was 29% below target due to poor equipment availability and wet ramps. The outlook for the upcoming quarter as the project enters the dry season is good with equipment availability set to improve as additional equipment is supplied by the mining contractor.

All mining quantities were down for the above reasons and, with the large stock piles in place, the focus was on waste stripping during the period, reflecting the high waste-to-ore ratio for the quarter. This will revert to normal for the coming dry season.

Ore availability on stockpiles (ROM pad) still remains in excess of five months of plant requirements at budget tonnes and grade.

Process Plant

Operating data

Leach recovery increased to 91.4% and acid consumption was maintained at budget with on site acid production meeting process requirements.

Resin management also remains a primary focus. Improvements in resin-in-pulp ("RIP") efficiency continued with 96.6% efficiency delivered. Improvements in RIP are largely the result of completion of the RIP Refurbishment Project, which allows additional contactors to be on line. In the coming quarter, continuous resin advance will be trialled with a view to full incorporation in the September quarter. It is expected that this will remove the RIP/Elution circuit as the principal process bottleneck and allow consistent performance at or above nameplate.

Overall recovery for the quarter increased to a record 87.2% as a result of the improved leach recovery and an improved RIP efficiency.

Production Optimisation

The two key optimisation projects identified in the last quarterly, grid power and acid recycling, are progressing well, although both have experienced minor delays. Notwithstanding the delays, costs remain within budget expectation.

Two further optimisation initiatives are also underway. As mentioned above, continuous resin advance will be trialled in the coming quarter with a view to full implementation in the following quarter. In addition to this initiative, the milling classification circuit is also being upgraded with a view to reducing milling power consumption and grind size. The reduced grind size will result in improved leach and RIP performance.

Exploration

Exploration concentrated on the preparation for the 2013 drilling programme. This programme will be larger than in previous years, with 20,000m of reverse circulation planned. Drilling will commence during this year's dry season.

UNIT COST IMPROVEMENT

Cost savings and optimisation initiatives through technical innovation continue to successfully reduce total costs and unit production costs at both mines.

PRODUCTION GUIDANCE FY2013

The continued solid and stable combined production over the past three quarters at LHM and KM of 6.11Mlb U3O8, with clear opportunities for continued improvement, place the Company in a good position to achieve its stated production target guidance of 8.0 to 8.5Mlb U3O8 for FY2013.

AURORA - MICHELIN URANIUM PROJECT, Canada (100%)

The Michelin winter infill drilling programme was completed with nine diamond holes for 3,272m. Uranium mineralisation occurs in strongly foliated felsic and mafic Aillik Group rocks in the N60 degrees E-striking, 50 degrees SE-dipping lenticular main zone and in two small hanging wall lenses. Drill intercepts from last summer and this winter targeting gaps in previous drilling generally showed more variable intercepts than expected. Hole M13-145 intersected 60m (at) 1,012ppm eU3O8 to confirm the core of the Michelin ore body. The updated resource estimate is planned for late June/early July. Some large approx. 100m gaps still exist in the southwest portion of Michelin and these will be targeted for summer drilling. Significant results from the recent winter drilling include:

Ground magnetic surveys were completed over swamps and lake areas not accessible in the summer period.

The complete ground survey will now help to develop new targets along the Michelin corridor, which extends 5km south west and northeast of the ore body.

MANYINGEE PROJECT, Australia (100%)

Evaluation of the 2012 drilling results is concentrating on developing an updated JORC-compliant resource and a new hydrogeological model to be used in any future in-situ recovery ("ISR") leach trial operations. An updated resource estimate is expected by June. Preparations have started for the 2013 drilling programme, which includes 10,000m rotary mud drilling to confirm and expand the resource base.

STRATEGIC INITIATIVE EFFORTS

Considerable effort has been applied to advancing the strategic initiative undertaken to unlock value from some of Paladin's assets. There is keen interest by the selected parties to become involved and the final phase has been entered.

As previously indicated, the proceeds from these initiatives will be applied to debt reduction and strengthening the balance sheet.

URANIUM MARKET COMMENTS

The Ux spot price moved in a narrow range during the quarter moving from a high of US$44.00/lb U3O8 in January before stabilising at US$42.25/lb U3O8 in March. The Ux term price was unchanged at US$56.00/lb U3O8 for the quarter.

Outlook

During this quarter, one new reactor, Hongyanhe-1, a 1000 MWe Pressurised Water Reactor (PWR) was connected to the grid in China, and formal construction started on Virgil C Summer-2 and Vogtle-3, both 1117 MWe PWR in the USA. Worldwide there are now 68 nuclear power plants under construction in 15 countries, which is six plants more than were under construction prior to the Fukushima accident in March 2011. With the exception of Japan, where there are still 48 plants offline pending the determination of new safety standards by the Nuclear Regulation Authority by July this year, the global nuclear fleet is performing well and is growing significantly in line with long-standing predictions.

Declaration

The information in this Announcement relating to exploration and mineral resources is, except where stated, based on information compiled by David Princep B.Sc who is a Fellow of the AusIMM. Mr Princep has sufficient experience that is relevant to the style of mineralisation and type of deposit under consideration and to the activity that he is undertaking to qualify as a Competent Person as defined in the 2004 Edition of the "Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves", and as a Qualified Person as defined in NI 43-101. Mr Princep is a full-time employee of Paladin Energy Ltd and consents to the inclusion of this information in the form and context in which it appears.

ACN 061 681 098



Contacts:
In Australia:
Paladin Energy Ltd
John Borshoff, Managing Director/CEO
+61 8 9381 4366
Mobile: +61 419 912 571


In Canada:
Paladin Energy Ltd
Greg Taylor, Investor Relations Contact
+905 337-7673 or Mobile: 416 605-5120 (Toronto)

Weitere Infos zu dieser Pressemeldung:

Themen in dieser Pressemitteilung:


Unternehmensinformation / Kurzprofil:
drucken  als PDF  an Freund senden  First Majestic Earns Socially Responsible Business Distinction Award for Fifth Consecutive Year Caledonia Mining Corporation: Restoration of Trading on AIM
Bereitgestellt von Benutzer: Marketwired
Datum: 17.04.2013 - 11:30 Uhr
Sprache: Deutsch
News-ID 249871
Anzahl Zeichen: 0

contact information:
Town:

PERTH, WESTERN AUSTRALIA



Kategorie:

Mining & Metals



Diese Pressemitteilung wurde bisher 258 mal aufgerufen.


Die Pressemitteilung mit dem Titel:
"Paladin Energy Ltd: Quarterly Activities Report For Period Ending-31 March 2013"
steht unter der journalistisch-redaktionellen Verantwortung von

Paladin Energy Ltd (Nachricht senden)

Beachten Sie bitte die weiteren Informationen zum Haftungsauschluß (gemäß TMG - TeleMedianGesetz) und dem Datenschutz (gemäß der DSGVO).


Alle Meldungen von Paladin Energy Ltd



 

Werbung



Facebook

Sponsoren

foodir.org The food directory für Deutschland
Informationen für Feinsnacker finden Sie hier.

Firmenverzeichniss

Firmen die firmenpresse für ihre Pressearbeit erfolgreich nutzen
1 2 3 4 5 6 7 8 9 A B C D E F G H I J K L M N O P Q R S T U V W X Y Z