First tower sections and nacelles for Global Tech I Wind Farm

First tower sections and nacelles for Global Tech I Wind Farm

ID: 288800

(PresseBox) - Construction of the Global Tech 1 Wind Farm commenced in September 2012. Its foundation structures are being transported to the construction site from BLG's offshore terminal at Bremerhaven with the installation vessel INNOVATION. Meanwhile, 51 of the 60 metre high tripods weighing 900 tons each have now been installed there.
Following the transport and intermediate storage of the foundation structures, with final assembly at WeserWind, for the Global Tech I wind park, BLG was commissioned by the construction company HOCHTIEF Solutions for the transport of the tower segments and nacelles. After loading the first tower segments of types S1 and S2 for the AREVA wind turbines onto the transport barge STRALSUND at the production site of Ambau GmbH in Bremen, BLG undertook the seafastening of the components and arranged their transport to the Fischereihafen at Bremerhaven.
Using its special SPMT (Self Propelled Modular Transporter) vehicles, BLG subsequently transported the nacelles and their associated components from their storage locations at the company AREVA Wind to the Labradorhafen and arranged their loading onto the pontoon. The pontoon was then towed to the ABC-Halbinsel offshore terminal. There, the components will shortly be transferred onto the installation vessel THOR which takes the components to the construction site and installs them at sea.



Unternehmensinformation / Kurzprofil:
drucken  als PDF  an Freund senden  Become a Master of Malbec With Trapiche Vineyards Moxa
Bereitgestellt von Benutzer: PresseBox
Datum: 19.08.2013 - 11:57 Uhr
Sprache: Deutsch
News-ID 288800
Anzahl Zeichen: 1430

contact information:
Town:

Bremen



Kategorie:

Ingredients



Diese Pressemitteilung wurde bisher 283 mal aufgerufen.


Die Pressemitteilung mit dem Titel:
"First tower sections and nacelles for Global Tech I Wind Farm"
steht unter der journalistisch-redaktionellen Verantwortung von

BLG LOGISTICS GROUP AG&Co. KG (Nachricht senden)

Beachten Sie bitte die weiteren Informationen zum Haftungsauschluß (gemäß TMG - TeleMedianGesetz) und dem Datenschutz (gemäß der DSGVO).

BLG exhibits in Copenhagen ...

From March 10 to 12, 2015, BLG LOGISTICS Group will be present at the European Wind Energy exhibition "EWEA Offshore" (Stand C4-C39) in Copenhagen, Denmark. The heavy-lift cargo handling segment BLG Wind Energy Logistics will showc ...

Alle Meldungen von BLG LOGISTICS GROUP AG&Co. KG



 

Werbung



Facebook

Sponsoren

foodir.org The food directory für Deutschland
Informationen für Feinsnacker finden Sie hier.

Firmenverzeichniss

Firmen die firmenpresse für ihre Pressearbeit erfolgreich nutzen
1 2 3 4 5 6 7 8 9 A B C D E F G H I J K L M N O P Q R S T U V W X Y Z