Santacruz Silver Announces Second Quarter 2014 Production Results
(firmenpresse) - Santacruz Silver Announces Second Quarter 2014 Production Results
Vancouver, B.C. - Santacruz Silver Mining Ltd. (TSX.V:SCZ) (the Company or Santacruz) is pleased to announce second quarter 2014 production of 169,800 payable silver equivalent ounces from the Companys Rosario Mine in San Luis Potosi, Mexico. This production represents a 40% quarter over quarter increase as compared with Q1 2014 payable silver equivalent ounces and the Company remains on schedule to meet its production target of between 850,000 to 1,100,000 silver equivalent ounces by the year-end 2014.
During the second quarter, the mine produced at an average daily rate of approximately 260 tonnes per day (tpd). By the end of the quarter, the mine was producing above 340 tpd as a daily average, while continuing to ramp up as more working faces are added into our production schedule. A chart summarizing the Rosario Minel total tonnes milled for January to June 2014 is available at the following link:
http://www.santacruzsilver.com/i/misc/2014-NR-664893-FIG1.jpg
Consistent with our planning, the Rosario Mine continues to see rapid improvements on many fronts including tonnes mined and milled. As our ratio of ore from stopes to development ore continues to increase, our mining cost will be reduced significantly stated Arturo Préstamo, CEO of Santacruz. In addition, our cost savings initiatives have started to produce results in the overall Rosario Mine operations. Cost savings is and will always be a very important part of our day-to-day operations and with that in mind, good consistent processes and practices are being established.
Second Quarter 2014 Operations Highlights (Compared to 1st Quarter 2014)
-Ore processed grew 10.5% to 22,612 tonnes (all ore milled is now from the Rosario Mine);
-Metal production increased 39.4% to 169,800 payable silver equivalent ounces ("Ag eq oz");
-Silver production totalled 100,200 silver ounces ("Ag oz");
-Underground development of 1,494 meters;
-Recoveries for silver increased to 89.9% from 85.7% in the first quarter.
2014 Second Quarter Operational Highlights
Operations Summary Q2 2014 Q1 2014 Change
Ore processed (tonnes 22,612 20,447 10.6%
milled)
Silver equivalent ounce 169,805 121,800 39.4%
production
1
Silver ounce production 100,200 94,325 5.9%
Gold ounce production 106.8 162.9 -34.9%
Lead production (tonnes) 171.7 186.1 -8.4%
Zinc production (tonnes) 436.8 367.6 15.9%
Total underground 1,494 1,216 22.83%
development
(m)
Note 1 EqAgOz=(Au*Pau/31.1035)+(Ag*Pag/31.1035)(+(Cu*Pcu*22.05)+(Pb*Ppb*22.05)+(Zn*Pzn*22.05)
(Pag)
Metal Prices: Ag $20, Au $1,250 Pb $0.96, Zn $0.88
Second Quarter 2014 Grade & Recovery Table
Au Ag Pb Zn
g/t %
0.21 153 0.86 2.29
Total Recoveries
70.4% 89.9% 88.2% 84.4%
Development Plan for 2014
Development at the Rosario Mine was steady with 1,494 metres of development completed in the quarter which is up 22.83% from Q1 2014. The focus was on developing the stopes on Level 2 and increasing the number of mining faces to have flexibility in the mine plan. In addition, the Company completed a sub-level between Level 2 and Level 3 which will provide additional mining faces and production as the main ramp continues to Level 3 by the end of this month. The competency of the rock has improved at depth and this will allow for more cost-effective and efficient development work to be completed.
For the balance of 2014, the Company will continue to focus on new stope production on the various levels that are being worked.
Qualified Person
All technical information included in this statement has been reviewed and approved by Donald E. Hulse P.E. of Gustavson Associates LLC. Mr. Hulse is independent of the Company and a qualified person, pursuant to the meaning of such terms in National Instrument 43-101 Standards of Disclosure for Mineral Projects.
About Santacruz Silver Mining Ltd.
Santacruz is a Mexican focused silver company with a producing mine (Rosario); two advanced-stage projects (San Felipe and Gavilanes) and an early-stage exploration project (El Gachi). The Company is managed by a technical team of professionals with proven track records in developing, operating and discovering silver mines in Mexico. Our corporate objective is to become a mid-tier silver producer.
signed
Arturo Préstamo Elizondo,
President, Chief Executive Officer and Director
For further information please contact:
Neil MacRae
Santacruz Silver Mining Ltd.
Email: info(at)santacruzsilver.com
Telephone: (604) 569-1609
TSX.V: SCZ
Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.
Forward looking information
Certain statements contained in this news release, such as planned production levels, grades, mine and mill development, mill recovery rates and the acquisition of mineralized material from third parties, constitute "forward-looking information" as such term is used in applicable Canadian securities laws. Forward-looking information is based on plans, expectations and estimates of management at the date the information is provided and is subject to certain factors and assumptions, including, that the Company's financial condition and development plans do not change as a result of unforeseen events, that the Company obtains regulatory approval, that the Company is able to obtain material from third parties on reasonable terms, future metal prices and the demand and market outlook for metals. Based on the Companys geological model and currently known mining blocks, the Company anticipates improved silver head grades and silver recoveries. Forward-looking information is subject to a variety of risks and uncertainties and other factors that could cause plans, estimates and actual results to vary materially from those projected in such forward-looking information. Factors that could cause the forward-looking information in this news release to change or to be inaccurate include, but are not limited to, the risk that any of the assumptions referred to prove not to be valid or reliable, that occurrences such as those referred to above are realized and result in delays, or cessation in planned work, that the Company's financial condition and development plans change, delays in regulatory approval, risks associated with the interpretation of data, the geology, grade and continuity of mineral deposits, the possibility that results will not be consistent with the Company's expectations, as well as the other risks and uncertainties applicable to mineral exploration and development activities and to the Company as set forth in the Company's Annual Information Form filed under the Company's profile at www.sedar.com. There can be no assurance that any forward-looking information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, the reader should not place any undue reliance on forward-looking information or statements. The Company undertakes no obligation to update forward-looking information or statements, other than as required by applicable law.
Rosario Mine
The decision to commence production at the Rosario Mine was not based on a feasibility study of mineral reserves demonstrating economic and technical viability, but rather on a more preliminary estimate of inferred mineral resources. Accordingly, there is increased uncertainty and economic and technical risks of failure associated with this production decision. Production and economic variables may vary considerably, due to the absence of a complete and detailed site analysis according to and in accordance with NI 43-101.
ROSARIO MILL
TOTAL TONNES MILLED
JANUARY-JUNE 2014
http://www.irw-press.at/prcom/images/messages/2014/7450/Jul 17 14 - Q2 2014 Production Results V4 - Final version_PR.001.png
Leseranfragen:
Santacruz ist ein Silberunternehmen mit einem Schwerpunkt auf Mexiko.




">

">
Datum: 17.07.2014 - 15:05 Uhr
Sprache: Deutsch
News-ID 334161
Anzahl Zeichen: 8809
contact information:
Town:
Wien
Kategorie:
Business News
Diese Pressemitteilung wurde bisher 300 mal aufgerufen.
Die Pressemitteilung mit dem Titel:
"Santacruz Silver Announces Second Quarter 2014 Production Results
"
steht unter der journalistisch-redaktionellen Verantwortung von
Santacruz Silver Mining Ltd. (Nachricht senden)
Beachten Sie bitte die weiteren Informationen zum Haftungsauschluß (gemäß TMG - TeleMedianGesetz) und dem Datenschutz (gemäß der DSGVO).