(firmenpresse) - PERTH, WESTERN AUSTRALIA -- (Marketwired) -- 06/03/15 -- Minerals and Energy Ltd ('GMEL' or 'the Company') (ASX: GGG)(OTC PINK: GDLNF)(FRANKFURT: G7P) is pleased to announce the maiden Ore Estimate for the Kvanefjeld Project. The reserve estimation has been produced by SRK Consulting (Australasia) Pty Ltd, who conducted an updated Study as part of the Kvanefjeld Feasibility Study (May, 2015). The Mining Study is supported by the , which was released in February 2015.
The Ore Reserves estimate has been developed to JORC 2012 standards as summarised in Table 1. The following constraints were applied to the estimate for the preparation of this statement:
Table 1. Kvanefjeld - May, 2015
The Ore Reserves are situated in the upper part of the Kvanefjeld Deposit, the largest of three defined within the broader project area. At the projected production rate of 3 million tonnes per annum, the Ore Reserves are sufficient to sustain 37 years of operation, inclusive of ramp-up.
Dr John Mair, Managing Director commented:
'An initial ore reserve of 108 million tonnes is an outstanding result, and is another really important project milestone. It takes a lot of work across numerous disciplines to achieve this level of confidence. The reinforces Kvanefjeld's status as one of the most advanced and significant emerging projects in the rare earth and uranium sectors globally.'
To see the full ASX announcement go to .
ABOUT GREENLAND MINERALS AND ENERGY LTD.
Greenland Minerals and Energy Ltd (ASX: GGG) is an exploration and development company focused on developing high-quality mineral projects in Greenland. The Company's flagship project is the Kvanefjeld multi-element deposit (, , ), that stands to be the world's premier specialty metals project. A comprehensive pre-feasibility study was finalised in 2012, and the feasibility study will be completed in 2015. The studies demonstrate the potential for a large-scale, cost-competitive, operation. Through 2015, GMEL is focussed on completing a mining license application in order to commence project permitting, in parallel to advancing commercial discussions with development partners.
Greenland Minerals and Energy Ltd will continue to advance the Kvanefjeld project in a manner that is in accord with both Greenlandic Government and local community expectations, and looks forward to being part of continued stakeholder discussions on the social and economic benefits associated with the development of the .
(ABN 85 118 463 004)
Contacts:
Greenland Minerals and Energy Ltd
Dr John Mair
Managing Director
+61 8 9382 2322
Professional PR
David Tasker
+61 8 9388 0944
Rostra Communication
Christian Olesen
+45 3336 0429
Themen in dieser Pressemitteilung:
Unternehmensinformation / Kurzprofil:
Bereitgestellt von Benutzer: Marketwired
Datum: 03.06.2015 - 05:47 Uhr
Sprache: Deutsch
News-ID 397777
Anzahl Zeichen: 0
contact information:
Town:
PERTH, WESTERN AUSTRALIA
Kategorie:
Mining & Metals
Diese Pressemitteilung wurde bisher 173 mal aufgerufen.
Die Pressemitteilung mit dem Titel:
"Maiden Ore Reserve of 108 Million Tonnes for Kvanefjeld Rare Earth - Uranium Project"
steht unter der journalistisch-redaktionellen Verantwortung von
Greenland Minerals and Energy Limited (Nachricht senden)
Beachten Sie bitte die weiteren Informationen zum Haftungsauschluß (gemäß TMG - TeleMedianGesetz) und dem Datenschutz (gemäß der DSGVO).