Stornoway Announces FY2016 First Quarter Results
(Thomson Reuters ONE) -
LONGUEUIL, Quebec, Sept. 14, 2015 (GLOBE NEWSWIRE) -- Stornoway Diamond
Corporation (TSX:SWY) (the "Corporation" or "Stornoway") announced today its
first quarter results for the three months ended July 31, 2015.
First Quarter FY2016 Highlights
(All quoted figures in CAD$)
* Construction at the Renard Diamond Project continues in line with the
planned schedule and budget.
* Incurred costs and commitments at the quarter-end totaled $402.6 million, or
50% of budget.
* Overall construction progress stood at 35% compared to a planned 33%.
Engineering progress stood at 80% compared to a planned 87%.
* On site manpower during the month of July averaged 329 workers, of which
24% were Crees of the Eeyou Istchee.
* At the end of the quarter principal construction on the process plant, power
plant, maintenance facility and primary crusher had been initiated and were
well advanced. Completion of the maintenance facility and enclosure of the
process plant are expected to be completed by the end of September and
October respectively, well within the planned schedule.
* During the quarter, the Corporation reported a net loss of $9.7 million or
$0.01 per share ($0.01 per share fully diluted).
* Cash, cash equivalents and short-term investments stood at $270.1
million([1]). Excess financing capacity available to complete the project,
comprising surplus cash and available cost-overrun facilities, is now
forecast to be $101 million, assuming the satisfaction of all covenants and
conditions precedent relating to future funding commitments and a CAD$:US$
conversion rate of $1.25.
Matt Manson, President and CEO, commented "During the latest quarter we
continued to make excellent progress on the construction of the Renard Project,
and are maintaining our forecast of completion within budget and schedule.
Construction progress continues to track ahead of plan, principal engineering is
nearing completion, and all major facilities are on track to be enclosed and
heated prior to the onset of cold weather conditions. In addition, we continue
to see an increase in the forecast amount of excess funding capacity available
to complete the project given our undrawn cost overrun facilities and the impact
of the depreciating Canadian dollar on the value of our current and committed US
dollar funds. This foreign exchange effect continues to influence our financial
results, through a fair value calculation on a portion of our carried debt and,
more importantly, offers the potential for an increasingly robust cash position
as we look to the project's commissioning and ramp-up period beginning late next
year."
Financial Summary
Stornoway ended the quarter with cash, cash equivalents and short-term
investments of $270.1 million, compared with $363.6 million at the end of the
previous quarter. Stornoway's current cash resources are sufficient to cover
planned mine development expenses, financing and corporate costs during calendar
2015. The second and third payment deposits under the stream agreement of US$80
and US$90 million are expected to be received in September 2015 and March 2016
respectively, following which Stornoway expects to draw on a $100 million senior
secured loan in late 2016 to complete mine development.
Assuming the full utilization of the senior secured loan, the Corporation
forecasts excess funding capacity of $101 million comprised of $53 million of
cash, receivables and expected mine tax credits and $48 million of undrawn cost
overrun facilities. This forecast assumes a project cost of $811 million (which
includes assumed levels of escalation and contingencies), the satisfaction of
all covenants and conditions precedent for future funding, and a CAD$:US$
exchange rate of $1.25 for unfunded US dollar denominated financing commitments.
As construction of the Renard Diamond Project progresses, this forecast is
expected to change quarter to quarter based on the timing of expenditures and
receipts, volatility in the CAD$:US$ exchange rate, and any change to the
forecast cost of the project. Capital expenditures incurred during the quarter
were $96.0 million, with capital expenditures to date of $402.6 million having
been committed against the total project cost.
Net loss for the three months ended July 31, 2015 decreased by $1.8 million to
$9.7 million compared to a loss of $11.5 million in the previous year, and
includes other income (expenses) of $7.3 million. Net losses were impacted by
several items not reflective of Stornoway's underlying operating performance,
including changes in the fair value of a derivative and unrealized gains and
losses from foreign exchange. Operating expenses for the three months ended
July, 2015 totaled $2.4 million.
Construction Highlights
At quarter end, overall construction progress stood at 35% based on man-hour
estimates compared to a planned 33%. Calendar 2015 construction activities
represent approximately 36% of the total execution plan, with 46% of the work
scheduled for 2016 and 3% for 2017. On July 31, engineering progress stood at
80% compared to a planned 87%. Engineering relating to the project's major
facilities is expected to be substantially complete by the end of September as
planned. No loss time incidents ("LTIs") were recorded during the quarter. One
restricted work injury incurred by a contractor in the prior quarter has been
reclassified subsequently as an LTI, for a project-to-date LTI rate of 0.9 for
contractors and 0.0 for Stornoway employees.
Construction of the project's process plant, maintenance facility, power plant
and primary crusher are well advanced. The maintenance facility is expected to
be substantially complete and operational on September 30, allowing the
maintenance of the major equipment currently being utilized in the mining
activities to relocate from temporary facilities approximately 6 months earlier
than was planned. The concrete pour for the natural gas fueled power plant began
on May 11 and structural steel erection began on August 6. All seven planned
2.055 MW Caterpillar LNG generators were delivered to the site by August 21.
Completion of the power plant is now scheduled for March 2016, allowing the
transition of on-site power supply from temporary diesel gen-sets to occur
several months earlier than expected.
Construction of the 2.2 million tonne per annum process plant represents the
project's critical path activity. The project's overall construction schedule
requires the plant building to be completed and heated by the fourth quarter of
calendar 2015, allowing the installation of the temperature sensitive crushing
and recovery circuits through the first half of calendar 2016. The concrete
foundations were completed on June 17, structural steel erection commenced on
June 15, and the building is expected to be fully enclosed and heated by October
30, allowing interior fitting to commence well ahead of plan. The plant is
scheduled to be energized in the second half of calendar 2016 with wet
commissioning beginning in the fourth quarter of that year. An 8 month
commissioning ramp-up is planned, with a view to commercial production being
achieved in the second quarter of calendar 2017 and full production by the
summer of 2017. The project remains on schedule to achieve these milestones.
Daily manpower at site in July averaged 329 workers, of which 24% were Crees of
the Eeyou Istchee. Stornoway employees, at site and in the development team,
stood at 274 on July 31, of which 18% were Crees, 22% were from Chibougamau and
Chapais, and 60% were from outside the region.
Mining
By quarter end, a total of 3,267,903 tonnes of overburden and waste rock had
been extracted from the Renard 2-Renard 3 and Renard 65 open pits, compared to a
budget of 3,724,211, or 88% of plan. Since April, mining activities have focused
on the Renard 2-Renard 3 pit with the Renard 65 pit serving as a sump for
surface water collection. The open pit mining team are now maintaining a
consistent production rate of more than 500,000 tonnes per month (542,593 tonnes
in July), with the new mining fleet performing well. Open pit mining of Renard
2 and Renard 3 during the construction phase of the project is expected to
result in the availability of a 700,000 tonne ore stockpile by the time plant
commissioning begins in late 2016. The project remains on schedule to achieve
this target.
Development of the ramp for the underground mine accelerated during the quarter
and stood at 486 meters on July 31 compared to a budget of 504 meters, or 96% of
plan. Delays experienced during March and April due to cold weather and
difficult initial ground conditions have now been essentially made-up, with
development during July achieving a rate of 122% of plan (164 meters compared to
a budget of 135 meters).
Renard Resource Update
During 2014, a resource expansion drill program was completed on the Renard 2
kimberlite with a view to convert Inferred Mineral Resources below the base of
the current Indicated Mineral Resource at 600 meters depth and the exploration
of additional kimberlite to depth. In total, 12,145 meters of deep directional
drilling was completed, with the deepest kimberlite intersection being at 1,012
vertical metres below surface. A revised Mineral Resource estimate for the
Renard Project incorporating the results of this work, and including updated
Mineral Resource estimates for the Renard 3 and 4 kimberlites and a revised
estimate of the further exploration potential of Renard kimberlites
1, 2, 3, 4, 7 and 10, is under final preparation and will be announced shortly.
Exploration Update
Stornoway retains an ownership interest in two diamond exploration projects
operated by North Arrow Minerals Inc. ("North Arrow"). During 2014, North Arrow
collected a sample of approximately 1,500 tonnes at the Qilalugaq Project in
Nunavut with a view to the recovery of a diamond parcel for valuation purposes.
On June 9, 2015 North Arrow announced that a 384 carat diamond parcel had been
estimated by WWW International Diamond Consultants to have an average price of
US$36 per carat, with a range of modeled values between a "possible low" of
US$43 per carat and a "possible high" of US$92 per carat. With the completion of
this work program North Arrow satisfied its earn-in obligations to the Qilalugaq
Project under the terms of its 2013 option agreement with Stornoway. On July
20, Stornoway informed North Arrow that it would not be exercising its back-in
right to the project, resulting in an 80-per-cent (North Arrow)/20- per-cent
(Stornoway) joint venture arrangement being formed. At this time, North Arrow
has not informed Stornoway of any potential future work programs at Qilalugaq.
Exploration is also being conducted with North Arrow at the Pikoo Project in
northern Saskatchewan. Kimberlites were first discovered at Pikoo in 2013
including the PK150 kimberlite which showed encouraging early microdiamond
counts. At time of writing, seven kimberlites have been drill confirmed and
microdiamond results from the PK314 kimberlite discovered during the winter
2015 drill program remain outstanding. Exploration of the Pikoo Project is being
conducted under an 80% (North Arrow) / 20% (Stornoway) participating joint
venture arrangement.
Summer exploration programs are ongoing on several 100% owned generative diamond
exploration projects in Canada with an overall budget for the current fiscal
year of $1 million. This work currently includes till sampling, prospecting and
claim acquisition. Further details on individual exploration programs will
follow should results warrant the commencement of ground geophysics and
drilling.
Financial Summary
Consolidated Statements of Financial Position
(millions of Canadian dollars) July 31, April 30,
2015 2015
Cash, cash equivalents and short-term investments 270.1 363.6
Property, plant and equipment 637.0 541.5
Other assets 39.9 40.0
Total Assets 947.0 945.1
Debt and convertible debentures 224.3 208.0
Deferred revenue 101.5 101.5
Other liabilities 52.0 58.1
Equity 569.2 577.5
Total Liabilities and Equity 947.0 945.1
Key Financial and Operating Highlights
(millions of Canadian dollars, except earnings Three Months Ended
(loss) per share and common shares outstanding)
July 31, 2015 July 31, 2014
Cash provided by (used in) operating activities (3440) (1438)
Cash used in investing activities (692) (25761)
Cash provided from (used in) financing (387) 436,934
activities
Effect of foreign exchange rate changes on cash 6,649 1,536
and cash equivalents
Net increase (decrease) in cash and cash 2,130 411,271
equivalent
Net loss for the period (9708) (11515)
Net loss per share - basic and diluted (0.01) (0.04)
Weighted Average Number of Common Shares issued 732,310,440 314,788,253
and outstanding (basic and diluted)
The Corporation's consolidated Financial Statements are prepared in Canadian
dollars in accordance with International Financial Reporting Standards.
Unaudited consolidated financial statements for the quarter ended July 31, 2015
and Management's Discussion and Analysis have been posted on the Corporation's
website www.stornowaydiamonds.com and on SEDAR at www.sedar.com.
About the Renard Diamond Project
The Renard Diamond Project is located approximately 250 km north of the Cree
community of Mistissini and 350 km north of Chibougamau in the James Bay region
of north-central Québec. On July 8th, 2014 Stornoway announced the completion of
a $946 million(([2])) project financing transaction to fully fund the project to
production, and construction commenced on July 10th, 2014. First ore is
scheduled to be delivered to the plant in the second half of 2016 with
commercial production scheduled for the 2nd quarter of 2017.
In January 2013, Stornoway released the results of an Optimized Feasibility
Study at Renard which highlighted the potential of the project to become a
significant producer of high value rough diamonds over a long mine life.
Probable Mineral Reserves, as defined in National Instrument 43-101 - Standards
of Disclosure for Mineral Projects ("NI 43-101"), stand at 17.9 million carats.
Total Indicated Mineral Resources, inclusive of the Mineral Reserve, stand at
27.1 million carats, with a further 16.85 million carats classified as Inferred
Mineral Resources, and 25.7 to 47.8 million carats classified as non-resource
exploration upside. Average annual diamond production is forecast at
1.6mcarats/year over the first 11 years of mining, at an average valuation of
US$190/carat based on a March 2014 assessment by WWW International Diamond
Consultants Ltd.
Readers are cautioned that the potential quality and grade of any target for
further exploration is conceptual in nature, there has been insufficient
exploration to define a Mineral Resource and it is uncertain if further
exploration will result in the target being delineated as a Mineral Resource.
All kimberlites remain open at depth. Readers are referred to the technical
report dated February 28th, 2013 in respect of the January 2013 Optimization
Study, and the press release dated July 23, 2013 in respect of the July 2013
Mineral Resource estimate, for further details and assumptions relating to the
project. Disclosure of a scientific or technical nature in this press release
was prepared under the supervision of Patrick Godin, P.Eng. (Québec), Chief
Operating Officer and Robin Hopkins, P.Geol. (NT/NU), Vice President,
Exploration, both "qualified persons" under NI 43-101.
[1] Assuming C$: US$ conversion rate of $1.3047
[2] For illustrative purposes. Assumes a C$: US$ conversion rate of $1.10.
Actual proceeds of each financing tranche are measured at the C$: US$ exchange
rate in effect the date the funds are received.
About Stornoway Diamond Corporation
Stornoway is a leading Canadian diamond exploration and development company
listed on the Toronto Stock Exchange under the symbol SWY and headquartered in
Montreal. Our flagship asset is the 100% owned Renard Diamond Project, on track
to becoming Québec's first diamond mine. Stornoway is a growth oriented company
with a world class asset, in one of the world's best mining jurisdictions, in
one of the world's great mining businesses.
On behalf of the Board
STORNOWAY DIAMOND CORPORATION
/s/ "Matt Manson"
Matt Manson
President and Chief Executive
This press release contains "forward-looking information" within the meaning of
Canadian securities legislation. This information and these statements, referred
to herein as "forward-looking statements," are made as of the date of this press
release and the Corporation does not intend, and does not assume any obligation,
to update these forward-looking statements, except as required by law.
These forward-looking statements include, among others, statements with respect
to Stornoway's objectives for the ensuing year, Stornoway's medium and long-term
goals, and strategies to achieve those objectives and goals, as well as
statements with respect to Stornoway's beliefs, plans, objectives, expectations,
anticipations, estimates and intentions. Although management considers these
assumptions to be reasonable based on information currently available to it,
they may prove to be incorrect.
Forward-looking statements relate to future events or future performance and
reflect current expectations or beliefs regarding future events and include, but
are not limited to, statements with respect to: (i) the amount of Mineral
Resources and exploration targets; (ii) the amount of future production over any
period; (iii) net present value and internal rates of return of the mining
operation; (iv) assumptions relating to recovered grade, average ore recovery,
internal dilution, mining dilution and other mining parameters set out in the
2011 Feasibility Study or the Optimization Study; (v) assumptions relating to
gross revenues, operating cash flow and other revenue metrics set out in the
2011 Feasibility Study or the Optimization Study; (vi) mine expansion potential
and expected mine life; (vii) expected time frames for completion of permitting
and regulatory approvals related to construction activities at the Renard
Diamond Project; (viii) the expected time frames for the completion of the open
pit and underground mine at the Renard Diamond Project; (ix) the expected time
frames for the completion of construction, start of mining and commercial
production at the Renard Diamond Project and the financial obligations or costs
incurred by Stornoway in connection with such mine development; (x) future
exploration plans; (xi) future market prices for rough diamonds; (xii) the
economic benefits of using liquefied natural gas rather than diesel for power
generation; (xiii) sources of and anticipated financing requirements; (xiv) the
effectiveness, funding or availability, as the case may require, of the Stream,
the Senior Secured Loan, the COF and the Equipment Facility and the use of
proceeds therefrom; (xv) the Corporation's expectations regarding receipt of the
remaining deposits under the Stream and its ability to meet its delivery
obligations thereunder; (xvi) the impact of the Financing Transactions on the
Corporation's operations, infrastructure, opportunities, financial condition,
access to capital and overall strategy; (xvii) the foreign exchange rate between
the US dollar and the Canadian dollar; and (xviii) the availability of excess
funding for the construction and operation of the Renard Diamond Project. Any
statements that express or involve discussions with respect to predictions,
expectations, beliefs, plans, projections, objectives, assumptions or future
events or performance (often, but not always, using words or phrases such as
"expects," "anticipates," "plans," "projects," "estimates," "assumes,"
"intends," "strategy," "goals," "objectives," "schedule," or variations thereof
or stating that certain actions, events or results "may," "could," "would,"
"might" or "will" be taken, occur or be achieved, or the negative of any of
these terms and similar expressions) are not statements of historical fact and
may be forward-looking statements.
Forward-looking statements are made based upon certain assumptions by Stornoway
or its consultants and other important factors that, if untrue, could cause the
actual results, performances or achievements of Stornoway to be materially
different from future results, performances or achievements expressed or implied
by such statements. Such statements and information are based on numerous
assumptions regarding present and future business prospects and strategies and
the environment in which Stornoway will operate in the future, including the
price of diamonds, anticipated costs and Stornoway's ability to achieve its
goals, anticipated financial performance, regulatory developments, development
plans, exploration, development and mining activities and commitments, and the
foreign exchange rate between the US and Canadian dollars. Although management
considers its assumptions on such matters to be reasonable based on information
currently available to it, they may prove to be incorrect. Certain important
assumptions by Stornoway or its consultants in making forward-looking statements
include, but are not limited to: (i) required capital investment and estimated
workforce requirements; (ii) estimates of net present value and internal rates
of return; (iii) receipt of regulatory approvals on acceptable terms within
commonly experienced time frames; (iv) anticipated timelines for completion of
construction, commencement of mine production and development of an open pit and
underground mine at the Renard Diamond Project, which heavily depend, among
other things, on adequate availability and performance of skilled labour,
engineering and construction personnel, performance of mining and construction
equipment and timely delivery of components; (v) anticipated geological
formations; (vi) market prices for rough diamonds and the potential impact on
the Renard Diamond Project; (vii) the satisfaction or waiver of all conditions
under each of the Stream, the Senior Secured Loan, the COF and the Equipment
Facility to allow the Corporation to draw on the funding available under those
financing elements for the completion of the development and construction of the
Renard Diamond Project; (viii) Stornoway's interpretation of the geological
drill data collected and its potential impact on stated Mineral Resources and
mine life; (ix) future exploration plans and objectives; (x) the receipt of the
remaining deposits under the Stream and the Corporation's ability to meet its
delivery obligations thereunder; and (xi) the continued strength of the US
dollar against the Canadian dollar. Additional risks are described in
Stornoway's most recently filed Annual Information Form, annual and interim
MD&A, and other disclosure documents available under the Corporation's profile
at: www.sedar.com.
By their very nature, forward-looking statements involve inherent risks and
uncertainties, both general and specific, and risks exist that estimates,
forecasts, projections and other forward-looking statements will not be achieved
or that assumptions do not reflect future experience. We caution readers not to
place undue reliance on these forward- looking statements as a number of
important risk factors could cause the actual outcomes to differ materially from
the beliefs, plans, objectives, expectations, anticipations, estimates,
assumptions and intentions expressed in such forward-looking statements. These
risk factors may be generally stated as the risk that the assumptions and
estimates expressed above do not occur, including the assumption in many
forward-looking statements that other forward-looking statements will be
correct, but specifically include, without limitation: (i) risks relating to
variations in the grade, kimberlite lithologies and country rock content within
the material identified as Mineral Resources from that predicted;
(ii) variations in rates of recovery and breakage; (iii) the uncertainty as to
whether further exploration of exploration targets will result in the targets
being delineated as Mineral Resources; (iv) developments in world diamond
markets; (v) slower increases in diamond valuations than assumed; (vi) risks
relating to fluctuations in the Canadian dollar and other currencies relative to
the US dollar; (vii) increases in the costs of proposed capital and operating
expenditures; (viii) increases in financing costs or adverse changes to the
terms of available financing, if any; (ix) tax rates or royalties being greater
than assumed; (x) uncertainty of results of exploration in areas of potential
expansion of resources; (xi) changes in development or mining plans due to
changes in other factors or exploration results; (xii) changes in project
parameters as plans continue to be refined; (xiii) risks relating to the receipt
of regulatory approvals or the implementation of the existing Impact and
Benefits Agreement with aboriginal communities; (xiv) the effects of competition
in the markets in which Stornoway operates; (xv) operational and infrastructure
risks; (xvi) execution risk relating to the development of an operating mine at
the Renard Diamond Project; (xvii) failure to satisfy the conditions to the
effectiveness, funding or availability, as the case may require, of each of the
Stream, the Senior Secured Loan, the COF and the Equipment Facility;
(xviii) changes in the terms of the Stream, the Senior Secured Loan, the COF or
the Equipment Facility; (xix) the funds of the Stream, the Senior Secured Loan,
the COF or the Equipment Facility not being available to the Corporation;
(xx) the Corporation being unable to meet its delivery obligations under the
Stream; (xxi) future sales or issuances of Common Shares lowering the Common
Share price and diluting the interest of existing shareholders; and (xxi) the
additional risks described in Stornoway's most recently filed Annual Information
Form, annual and interim MD&A and Stornoway's anticipation of and success in
managing the foregoing risks. Stornoway cautions that the foregoing list of
factors that may affect future results is not exhaustive, and new, unforeseeable
risks may arise from time to time.
CONTACT: For more information, please contact Matt Manson (President and CEO) at
416-304-1026 x2101 or Orin Baranowsky (Director, Investor Relations) at
416-304-1026 x2103 or toll free at 1-877-331-2232
Pour plus d'information, veuillez contacter M. Ghislain Poirier, Vice-president
Affaires publiques de Stornoway au 418-254-6550, gpoirier(at)stornowaydiamonds.com
** Website: www.stornowaydiamonds.com
Email: info(at)stornowaydiamonds.com **
This announcement is distributed by GlobeNewswire on behalf of
GlobeNewswire clients. The owner of this announcement warrants that:
(i) the releases contained herein are protected by copyright and
other applicable laws; and
(ii) they are solely responsible for the content, accuracy and
originality of the information contained therein.
Source: Stornoway Diamond Corporation via GlobeNewswire
[HUG#1952017]
Unternehmensinformation / Kurzprofil:
Bereitgestellt von Benutzer: hugin
Datum: 15.09.2015 - 03:03 Uhr
Sprache: Deutsch
News-ID 419955
Anzahl Zeichen: 30800
contact information:
Town:
Longueuil, Québec
Kategorie:
Business News
Diese Pressemitteilung wurde bisher 142 mal aufgerufen.
Die Pressemitteilung mit dem Titel:
"Stornoway Announces FY2016 First Quarter Results"
steht unter der journalistisch-redaktionellen Verantwortung von
Stornoway Diamond Corporation (Nachricht senden)
Beachten Sie bitte die weiteren Informationen zum Haftungsauschluß (gemäß TMG - TeleMedianGesetz) und dem Datenschutz (gemäß der DSGVO).





