Sovereign Metals: Malingunde PFS Delivers Lowest Operating Cost Coarse Flake Graphite Project Globally
(firmenpresse) - Sovereign Metals: Malingunde PFS Delivers Lowest Operating Cost Coarse Flake Graphite Project Globally
Sovereign Metals Limited (the Company or Sovereign) is pleased to announce the Pre-Feasibility Study (PFS) for the Companys Malingunde Saprolite-Hosted Graphite Project (Malingunde Project or the Project) in Malawi. The PFS shows the Projects low capital and very low operating costs are at the bottom of the graphite supply cost-curve at a scale appropriate for the current market.
https://www.irw-press.at/prcom/images/messages/2018/45115/181107 Malingunde PFS_FINAL (low res)PRcom.001.png
The PFS confirms Malingundes world-class status based on the following:
- Maiden Ore Reserve declared: high grade Reserve with 32% in the Proven and 68% in the Probable categories. PFS based 100% on Reserves.
- Extremely low operating costs: due to the advantages of the soft saprolite-hosted deposit.
- US$323/t concentrate (FOB) LoM average, moving to as low as US$284/t after year 7.
- Mine gate LoM average US$257/t moving to as low as US$218/t after year 7.
- Low technical risk: free-dig mining, low strip ratio with simple, proven process flowsheet.
- High-quality concentrates: sales targeted to traditional industrial sector (refractories, foundries, expandables) as well as the emerging Li-ion battery sector.
- Substantial upside: huge scalability and expansion opportunities.
Sovereigns Managing Director, Dr Julian Stephens, said We believe Malingunde is the worlds best flake graphite project. The high-grade, soft, free-dig saprolite-hosted ore, requiring no primary crush or grind combined with a simple and proven flowsheet results in low capital intensity and extremely low operating costs. Malingunde is an unparalleled, low technical risk, high margin project that provides significant cashflows with substantial upside scalability into a growing graphite market.
ENQUIRIES ---
Dr Julian Stephens - Managing Director
Sam Cordin - Business Development Manager
+618 9322 6322--
Extremely Low Operating & Low Capital Costs, High Margins
- Average LOM (life of mine) operating costs of US$323/t concentrate FOB with long-term, steady-state operating costs averaging as low as US$284/t FOB (year 7 to end LoM).
- High quality product with ~60% +150µm, 96-98% TGC commanding high revenues.
- Total capital cost of US$49 million including contingency of US$5m.
- NPV of US$201m pre-tax, using conservative long-term average basket pricing assumption of US$1,216 per tonne of concentrate.
- Average EBITDA over US$42m per annum over LoM.
- Payback: 3.0 years from start of production.
Excellent Existing Infrastructure
- Recently refurbished rail line to Nacala Port: MOU signed with rail concessionaire - drafting of full transport agreement currently underway.
- High quality existing road network to site: mostly bitumen with ~10km all-weather gravel road.
- 10km from planned Bunda electricity sub-station, 44km from new Nkhoma sub-station: grid power provision slated for 2024.
Strong Relationships and Partnerships
- Project located in the mining friendly jurisdiction of Malawi. Strong government and community support with long standing relationships.
- Rail and port export logistics partnership with CEAR (controlled by Vale and Mitsui).
- Well advanced sales negotiations with numerous Tier 1 and other high quality off-take parties across a number of industrial sectors and global locations.
Commentary
Sovereigns 100%-owned Malingunde saprolite-hosted graphite project is a globally significant, coarse flake graphite development. It represents a high quality potential future mining operation producing premium quality natural graphite products. The PFS demonstrates extremely low operating and low capital costs providing excellent margins. The compelling economic estimates can be attributed to the deposit being hosted entirely by soft saprolite material, its high grade at 9.5% TGC and the excellent infrastructure availability.
Soft-saprolite hosted graphite deposits are sought after as they have distinct operating and capital cost advantages over hard-rock deposits. Currently operating saprolite-hosted flake graphite mines are located in Madagascar, however these are mostly small and low grade (typically 4-6% TGC). Malingunde is rare in that it is the worlds largest reported saprolite-hosted flake graphite deposit and also has a high-grade ore reserve at 9.5% TGC.
The PFS shows that Malingunde offers a technically and economically robust, low risk pathway to production of premium quality, coarse flake graphite concentrates. The significant cost savings, compared to hard-rock peers, are realised by the soft, free dig nature of the mineralisation and low strip ratios, with no requirement for primary crushing or grinding in the processing plant. Additionally, the project is located just 20km from Lilongwe, the capital of Malawi, which brings with it access to important infrastructure including rail and grid power.
https://www.irw-press.at/prcom/images/messages/2018/45115/181107 Malingunde PFS_FINAL (low res)PRcom.002.png
Figure 1: The Saprolite Advantage
TABLE 1 - KEY PROJECT METRICS
MALINGUNDE PROJECT PARAMETERS Unit Estimated Value
ECONOMIC
Development capital US$m 33
Indirect costs & contingency US$m 16
Total development capital US$m 49
Sustaining capital (over US$m 23
life-of-mine)
Mine gate opex. (LoM, ex. US$/t 257
royalties, conc.
inc. G&A)
Transport & logistics cost US$/t 66
conc
Average LOM operating cost (FOB NaUS$/t 323
cala conc
)1
PHYSICAL
Average annual plant throughput tpa 600,000
Average annual concentrate tpa 52,000
production
LoM average feed grade % 9.5%
LoM average product grade % TGC 97.0%
LoM average recovery % 90%
Mine life Years 16
LoM average strip ratio (inclusivewaste : 1.0
of ore
capitalised pre-strip)
FINANCIAL
NPV (10%) - Pre-tax US$m 201
NPV (10%) - Post-tax US$m 141
IRR - Pre-tax % 56
IRR - Post-tax % 43
Basket price applied US$/t 1,216
conc.
EBITDA average LoM US$m 42
EBITDA average long term (after US$m 45
year
7)
Annual revenue average (post US$m 62
ramp-up)
Notes:
1. LoM operating cost: cost per tonne including mining, processing, G&A and transportation.
EXTREMELY LOW, FIRST QUARTILE CASH OPERATING COSTS
The Malingunde PFS estimates operating costs of approximately US$323 per tonne concentrate free on board (FOB), or US$257 at mine gate (MG), for its high quality graphite concentrates at a production rate averaging 52,000 tonnes per annum over the life of mine. Additionally, estimated long term average costs move to just US$284 FOB or US$218 MG after year 7. The project has the lowest estimated unit operating cost of the current and future listed graphite development pipeline, at a reasonable scale that can easily be placed into existing traditional markets and the growing battery supply chain.
https://www.irw-press.at/prcom/images/messages/2018/45115/181107 Malingunde PFS_FINAL (low res)PRcom.003.png
Figure 2: Operating cost per tonne of graphite concentrate versus selected ASX & TSX-listed peer companies.
LOW CAPITAL COSTS
The results of the PFS demonstrate low overall capital requirements and low capital intensity. This allows rapid payback of development capital, even in low global graphite pricing scenarios. This is a significant advantage in terms of seeking potential offtake partners and financing for development.
https://www.irw-press.at/prcom/images/messages/2018/45115/181107 Malingunde PFS_FINAL (low res)PRcom.004.png
Figure 3: Capital intensity versus selected, listed peer projects.
LOW COST, HIGH MARGIN OPERATION AT MARKETABLE SCALE
Sovereign is in a unique position of being able to target profitable production of graphite without relying on extreme size to achieve economies of scale, or assuming optimistic product pricing scenarios.
The Company has taken a deliberately conservative view for its base-case PFS scenario on graphite pricing. Using these assumptions, the PFS shows high operating margins and significant cash generation. Importantly, downside pricing scenarios also show good margins and short payback periods, meaning the project is profitable even in extremely low global graphite market pricing conditions.
The combination of very low operating cost, low capital cost and high quality, high value concentrates allows Sovereign to focus on entry into existing primary end-markets, including refractories and foundries. The low-cost profile of the Malingunde Project means it is able to compete on price point with China, the worlds largest supplier and consumer of natural flake graphite.
The Project is also exposed to the strongly emerging Lithium-ion battery market with significant forecasted upside. Recent test-work demonstrated very high purity (five nines +99.999% C) graphite is easily achievable, facilitating future entry into the lithium-ion battery supply chain and other high-tech, emerging industries.
https://www.irw-press.at/prcom/images/messages/2018/45115/181107 Malingunde PFS_FINAL (low res)PRcom.005.png
Figure 4: Production scale, operating costs and capital costs of key undeveloped graphite projects.
To view the entire original news including all tables and appendices, please follow the link:
https://www.asx.com.au/asxpdf/20181107/pdf/44028jwmjqmqz0.pdf
Leseranfragen:
Datum: 07.11.2018 - 08:33 Uhr
Sprache: Deutsch
News-ID 583599
Anzahl Zeichen: 10745
contact information:
Town:
Wien
Kategorie:
Business News
Diese Pressemitteilung wurde bisher 286 mal aufgerufen.
Die Pressemitteilung mit dem Titel:
"Sovereign Metals: Malingunde PFS Delivers Lowest Operating Cost Coarse Flake Graphite Project Globally
"
steht unter der journalistisch-redaktionellen Verantwortung von
Sovereign Metals Limited (Nachricht senden)
Beachten Sie bitte die weiteren Informationen zum Haftungsauschluß (gemäß TMG - TeleMedianGesetz) und dem Datenschutz (gemäß der DSGVO).