Tipper Trucks Start Journey to Gounkoto Mine
(firmenpresse) - JERSEY, CHANNEL ISLANDS and DAKAR, SENEGAL -- (Marketwire) -- 09/22/11 --
Eleven specially modified 50
tonne trucks have arrived in Dakar in Senegal en route to the new
Gounkoto gold mine at Randgold Resources' Loulo mining complex in
Western Mali.
The ship carrying the Volvo FMX 10x4 tipper trucks which were
purpose-built for the mine by BAS Volvo Trucks in the Netherlands,
docked in Dakar this morning. Modifications to the trucks include the
addition of a fifth axle and a customised tray with an innovative
hardox 500 bottom ware plate system. Three further trucks have been
ordered and are scheduled to arrive in Dakar in February next year,
bringing Randgold's total investment in the fleet to US$4.2 million.
Transporting these haulage trucks from Dakar harbour to the mine in
Mali is being controlled by local Senegalese logistics partner Lamine
Gueye of CSTTAO.
The trucks will be used to transport ore from the Gounkoto mine to the
plant at Loulo, some 30 kilometres away. "This dedicated fleet will
greatly reduce the cost per tonne of ore delivered to Loulo as a result
of the increased hauling capacity and efficient fuel consumption," says
Randgold group consulting mining engineer Marcel Damen.
Gounkoto which progressed from discovery to production in just 30
months, poured its first gold in June this year, contributing more than
14 000 ounces of gold to the Loulo mine complex's output in its first
month of production. Diversion dams and flood berm protection for the
open pit were completed before the start of the rainy season. In
addition, the haul road to Loulo was established with water control
measures such as bridges and culverts. Open pit mining operations are
now fully functioning, 24 hours a day, seven days a week. Construction
of permanent crushing facilities at Gounkoto is nearing completion with
a mobile crusher being used in the meantime.
The upgrade to the Loulo plant is also progressing well and remains on
track for completion by the end of the year. Additional power
generation units are being installed, which will supply the Gounkoto
mine as well as the new mill at Loulo. Foundations and civil work for
the third mill are well advanced. "Gounkoto brings flexibility and is
expected to contribute to an improving production trend from the Loulo
complex over the next few quarters," says Randgold CEO Mark Bristow."Along
with Yalea, Gara and Loulo 3, Gounkoto is part of a big and
highly prospective region which stretches from Baboto in the north to
Faraba down in the south. With the open pit in production, explorationwork
at Gounkoto has continued to target the underground potential
beneath the pit. Regional exploration is also continuing with the aim
of not only extending our existing asset base at Loulo but to discover
more Gounkotos," Bristow said.
CAUTIONARY NOTE REGARDING FORWARD-LOOKING STATEMENTS: Except for the
historical information contained herein, the matters discussed in this
news release are forward-looking statements within the meaning of
Section 27A of the US Securities Act of 1933 and Section 21E of the US
Securities Exchange Act of 1934, and applicable Canadian securities
legislation. Forward-looking statements include, but are not limited
to, statements with respect to the future price of gold, the estimation
of mineral reserves and resources, the realisation of mineral reserve
estimates, the timing and amount of estimated future production, costs
of production, reserve determination and reserve conversion rates.
Generally, these forward-looking statements can be identified by the
use of forward-looking terminology such as 'will', 'plans', 'expects'
or 'does not expect', 'is expected', 'budget', 'scheduled','estimates',
'forecasts', 'intends', 'anticipates' or 'does not
anticipate', or 'believes', or variations of such words and phrases or
state that certain actions, events or results 'may', 'could',
'would','might' or 'will be taken', 'occur' or 'be achieved'. Assumptions
upon
which such forward-looking statements are based are in turn based on
factors and events that are not within the control of Randgold and
there is no assurance they will prove to be correct. Forward-looking
statements are subject to known and unknown risks, uncertainties and
other factors that may cause the actual results, level of activity,
performance or achievements of Randgold to be materially different from
those expressed or implied by such forward-looking statements,
including but not limited to: risks related to the integration of
Randgold and Moto, risks related to mining operations, including
political risks and instability and risks related to international
operations, actual results of current exploration activities,
conclusions of economic evaluations, changes in project parameters as
plans continue to be refined, as well as those factors discussed in the
section entitled 'Risk Factors' in Randgold's annual report on Form
20-F for the year ended 31 December 2010 which was filed with the US
Securities and Exchange Commission (the 'SEC') on 31 March 2011.
Although Randgold has attempted to identify important factors that
could cause actual results to differ materially from those contained in
forward-looking statements, there may be other factors that cause
results not to be as anticipated, estimated or intended. There can be
no assurance that such statements will prove to be accurate, as actual
results and future events could differ materially from those
anticipated in such statements. Accordingly, readers should not place
undue reliance on forward-looking statements. Randgold does not
undertake to update any forward-looking statements herein, except in
accordance with applicable securities laws.
CAUTIONARY NOTE TO US INVESTORS: the SEC permits companies, in their
filings with the SEC, to disclose only proven and probable ore
reserves. We use certain terms in this release, such as 'resources',
that the SEC does not recognise and strictly prohibits us from
including in our filings with the SEC. Investors are cautioned not to
assume that all or any parts of our resources will ever be converted
into reserves which qualify as 'proven and probable reserves' for the
purposes of the SEC's Industry Guide number 7.
This information is provided by RNS
The company news service from the London Stock Exchange
END
RANDGOLD RESOURCES ENQUIRIES:
Chief Executive
Mark Bristow
+44 788 071 1386
+44 779 775 2288
Technical & Capital Executive
John Steele
+223 66 75 90 54
+27 83 308 9990
Group Operations
Manager: West Africa
Samba Toure
+223 66 75 77 41
+223 20 20 16 94
Investor & Media Relations
Kathy du Plessis
+44 20 7557 7738
Website:
Themen in dieser Pressemitteilung:
Unternehmensinformation / Kurzprofil:
Bereitgestellt von Benutzer: MARKET WIRE
Datum: 22.09.2011 - 14:35 Uhr
Sprache: Deutsch
News-ID 68743
Anzahl Zeichen: 0
contact information:
Town:
JERSEY, CHANNEL ISLANDS and DAKAR, SENEGAL
Kategorie:
Mining & Metals
Diese Pressemitteilung wurde bisher 215 mal aufgerufen.
Die Pressemitteilung mit dem Titel:
"Tipper Trucks Start Journey to Gounkoto Mine"
steht unter der journalistisch-redaktionellen Verantwortung von
Randgold Resources Ld (Nachricht senden)
Beachten Sie bitte die weiteren Informationen zum Haftungsauschluß (gemäß TMG - TeleMedianGesetz) und dem Datenschutz (gemäß der DSGVO).





