(firmenpresse) - TIVERTON, ONTARIO -- (Marketwire) -- 03/20/12 -- Earlier this morning, Bruce Power's operations team removed reactor shutdown guarantees on Unit 2 following completion of minor repairs to a pump system.
As previously reported, following CNSC approval on Friday, which allowed Bruce Power to remove shutdown guarantees on Unit 2, the company's operations team detected a leak on a Unit 2 pump system during restart activities. Bruce Power took appropriate actions to safely and quickly isolate the leak as per the company's operating procedures.
There was no impact on the rest of Bruce A, the public, external environment or worker safety.
The company will continue with the return to operations program on both Units 1 and 2, which will involve the powering-up and commissioning of many complex systems in preparation to provide 1,500 megawatts of additional electricity for the province.
About Bruce Power
Bruce Power is a partnership among Cameco Corporation, TransCanada Corporation, BPC Generation Infrastructure Trust, a trust established by the Ontario Municipal Employees Retirement System, the Power Workers' Union and The Society of Energy Professionals.
Contacts:
Bruce Power
John Peevers
519-361-6583
Bruce Power
24-hour Duty Media Officer
519-361-6161
Themen in dieser Pressemitteilung:
Unternehmensinformation / Kurzprofil:
Bereitgestellt von Benutzer: MARKETWIRE
Datum: 20.03.2012 - 13:17 Uhr
Sprache: Deutsch
News-ID 126547
Anzahl Zeichen: 0
contact information:
Town:
TIVERTON, ONTARIO
Kategorie:
Alternative Energy
Diese Pressemitteilung wurde bisher 209 mal aufgerufen.
Die Pressemitteilung mit dem Titel:
"Bruce Power: Update on Unit 2 Return to Operations"
steht unter der journalistisch-redaktionellen Verantwortung von
Bruce Power (Nachricht senden)
Beachten Sie bitte die weiteren Informationen zum Haftungsauschluß (gemäß TMG - TeleMedianGesetz) und dem Datenschutz (gemäß der DSGVO).