QUARTERLY ACTIVITIES REPORT FOR THE PERIOD ENDED 31 MARCH 2014
(firmenpresse) -
QUARTERLY ACTIVITIES REPORT FOR THE PERIOD ENDED 31 MARCH 2014
30 April 2014 ASX AnnouncementASX Code: SFZ
Highlights:
· Record quarterly sales volumes of 317,046 tonnes of beneficiated product, an increase of 34% from the previous quarter.
· Implementation of cost reduction and efficiency programmes aimed at reducing production costs to $21 per tonne by May 2014.
· Significant progress on Bankable Feasibility Study.
SAFMs Managing Director, Stephen Turner commented:
Significant progress has been made on the Bankable Feasibility Study during the quarter including the completion of magnetic separation test works and the definition of the water capture system. At the end of the quarter, SAFM collated all final study schedules from the various principal consultants and contractors, with the aim of completing the Study by the third quarter of this year. The company is concurrently evaluating various financing alternatives, involving a combination of debt, equity, state subsidies and prepayment of offtake agreements.
Licence applications have been submitted to the various government authorities and construction approvals are expected to be issued prior to the BFS completion in the third quarter of 2014.
It was pleasing to see the improvements at the mine, with enhanced grades and reduced production costs. The production of higher grades has led to a widening in SAFMs customer base and an increase in sales, thus also resulting in a reduction of stockpiles and an increase in the cash generated from operations.
Commodity-TV Interview with Alan Doyle: http://bit.ly/1eYPunJ
South American Ferro Metals Limited (ASX: SFZ) (SAFM or the Company) provides the following commentary for the three months ended 31 March 2014, to be read in conjunction with Appendix 5B.
1. Expansion project
Primary developments over the quarter were as follows:
· The necessary metallurgical test work required for the Bankable Feasibility Study (BFS) is now complete. Variability test work is being finalised in order to verify plant design factors.
· RMC, a Brazilian mining consulting company is completing the Mining Feasibility Study.
· Pipeline routes have been agreed. Hydraulic calculations and equipment sizing have been completed.
· The rail-load terminal design is being finalised by a local company certified by Rail Operator, MRS and anticipated to be completed by June 2014.
· The final environmental licensing strategy was defined. It is anticipated that the installation licences will be granted within the next quarter.
· CEMIG has completed the design of the Power Transmission Line route from grid substation to the SAFM HV switchyard.
The collation of all final study schedules from the various principal consultants and contractors was received at the end of the quarter. The reaching of this milestone in the analysis phase of the project triggers the beginning of the projects financing phase with the evaluation of financing alternatives, including debt, equity, state subsidies and prepayment of offtake.
2. Production volumes
Dec 13 Mar 14 MovemenMovemen
Qtr Qtr t t
(tonnes)(tonnes
)
(tonnes(%)
)
ROM production 445,759 339,644(106,11(23%)
5)
Beneficated production 246,190 192,820(53,370(21%)
)
Finished stock at end of 160,594 27,990 (132,60(82%)
Quarter 4)
SAFM recorded lower production, due to seasonal rains during the March 2014 quarter, the reconfiguration of mechanical equipment and the implementation of production adjustments aimed at improving product quality.
The grade of all products increased markedly with minimum product specifications achieved for all product categories. This improvement in product quality resulted in an increase in selling prices of all products.
3. Sales volumes
Dec 13 Mar 14 MovemenMovemen
Qtr Qtr t t
(tonnes)(tonnes
)
(tonnes(%)
)
Sinter Feed 65,006 126,20661,200 94%
Lump 53,730 80,456 26,726 50%
Concentrate 118,250 110,384(7,866)(7%)
Total sales of 236,986 317,04680,060 34%
Beneficiated
product
Sales of beneficiated product increased by 34% during the March 2014 quarter to 317,046 tonnes. The high sales volumes resulted in a significant drop in stockpiles. Selling prices increased by an average of 10.6% in the March 2014 quarter reflecting the improvement in product grade referred to above.
4. Cost reduction programme
During the quarter, SAFM continued to implement cost reduction measures and efficiency enhancement programmes. Some of the actions implemented include a reduction in staff numbers and fleet size, stringent cost cutting exercises and a focus on improving mass recovery. The goal of the programmes is to reduce the production unit cost to $21 per tonne by May 2014.
5. Safety and Environment
SAFM has implemented a series of safety improvements including re-designing the routes of trucks and heavy equipment inside the Ponto Verde Mine site, installing plant barriers and purchasing new safety equipment for employees.
SAFMs safety and environmental performance underpins the Companys license to operate and grow in Brazil. There was no lost time due to injuries during the quarter.
6. Cash Flow from Operations
SAFM recorded a positive net operating cash flow from operations of $2.67 million for the March 2014 quarter. The Companys capital projects utilised cash expenditure of $3.2 million, mostly related to the settlement of the waste and tailings property and Bankable Feasibility Study. The companys cash balance at the end of the quarter was $4.1 million.
For more information:
South American Ferro Metals Limited
Stephen Turner (Managing Director)
Ph: +61 2 8298-2004 or +61 (0) 418 440 844.
About South American Ferro Metals Limited:
South American Ferro Metals Limited owns 100% of the mineral rights and property of the Ponto Verde Iron Ore Project in Brazil. Ponto Verde is located in the heart of the Iron Ore Quadrilateral, 55 kilometres from the town of Belo Horizonte in the state of Minas Gerais. The Iron Ore Quadrilateral is a prolific iron ore mining area, and the Project is located proximate to established mining operations, iron and steel plants and existing infrastructure.
SAFM currently sells three iron ore products from its Ponto Verde mine to local steel producers in Brazil. The Company is currently completing its Bankable Feasibility Study (BFS) to expand Ponto Verde to a capacity of 8 Mtpa ROM throughput, from its current 1.5 Mtpa licenced capacity. The BFS is expected to be completed by the third quarter of 2014.
Forward Looking Statements
This announcement contains certain forward looking statements which by nature, contain risk and uncertainty because they relate to future events and depend on circumstances that occur in the future. There are a number of factors that could cause actual results or developments to differ materially from those expressed or implied by these forward looking statements.
Website: www.safml.com
Leseranfragen:
South American Ferro Metals Limited gehören 100% der mineralischen Rechte und das Grundstück des Ponto Verde Eisenerzprojektes in Brasilien.
Datum: 02.05.2014 - 14:22 Uhr
Sprache: Deutsch
News-ID 330991
Anzahl Zeichen: 8265
contact information:
Town:
Wien
Kategorie:
Business News
Diese Pressemitteilung wurde bisher 314 mal aufgerufen.
Die Pressemitteilung mit dem Titel:
"QUARTERLY ACTIVITIES REPORT FOR THE PERIOD ENDED 31 MARCH 2014
"
steht unter der journalistisch-redaktionellen Verantwortung von
South American Ferro Metals (Nachricht senden)
Beachten Sie bitte die weiteren Informationen zum Haftungsauschluß (gemäß TMG - TeleMedianGesetz) und dem Datenschutz (gemäß der DSGVO).