Endomines AB Press Release, Summary of interim report January - June 2010
(Thomson Reuters ONE) -
Pampalo Gold Mine construction progressing on schedule
Summary of events
Pampalo Gold Mine:
* Pampalo Gold Mine construction continues in-line with the budget, with some
minor overruns due to quality-improvements with regards to the crushing
circuit and mine site laboratory
* Underground infill drilling assay results were received in April, and the
production area for the first two to three years of production was
delineated.
* Major building works were completed in May.
* Installation of processing plant equipment commenced in May as scheduled.
* A Shareholders Day was held at 19th June at Pampalo Gold Mine.
Company overview:
* MSc (Mining Engineering) Rauno Pitkänen was elected as a new board member
after Per Torell's resignation at the Annual General Meeting.
* Endomines Board of Directors has decided to write-down Kälviä ilmenite
assets 44,993 KSEK.
* The current market value of Endomines' gold price and interest rate hedge
programs is -168 169 KSEK, mainly due to the strengthening of the gold price
in dollar and the weaker Euro.
Operations overview
Construction of the Pampalo Gold Mine continued efficiently during the second
quarter of 2010.
All assay results from a 43 holes, 2,727-meter diamond-core drilling campaign at
the Pampalo underground gold mine were received in April. These results confirm
the planned production start-up schedule, with test production commencing at the
end of 2010, and full-scale production in the first quarter of 2011.
The completed infill drilling campaign will allow production down to 320-meter
levels without any additional diamond core drilling. The ore has now been
delineated to cover the first two-three years of production. The new results
will also be used for the Pampalo mine ore reserve estimation that is currently
under preparation by independent qualified consultants.
Major building works were completed in early May according to schedule and
within budget despite the very cold winter conditions. The first batch of
processing equipment containing flotation cells from Metso Minerals Sala AB was
received in May. All equipment deliveries and installation have happened
according to project schedule.
Underground development works continued with ventilation raise drifting as well
as drifting in ore and waste rock. The ore from development drifting has been
regularly sampled and these have returned grades, which comply with the expected
grades from respective areas. All ore derived from development drifting will be
stockpiled for further processing and gold production after the processing plant
and power line have been commissioned.
The erection of the new 47-kilometre power line from Ratilanvaara to the Pampalo
Gold Mine site is progressing ahead of schedule. The line is expected to be
commissioned well before year-end, which will allow for efficient test
production to commence during Q4/2010.
A Shareholders' Day was held on June 19th, attended by about 50 shareholders
from Finland and Sweden.
There was one lost time accident in the underground mine during the reporting
period resulting for three days sick leave. The total work force on-site has
been on average 15 Endomines and 46 contractor employees.
Kälviä Ilmenite assets write down
Endomines' Board of Directors has recently carried out a thorough market study
and analysis of the Kälviä ilmenite assets, including commissioning a study
conducted by independent consultants. As a result, and particularly due to the
fact that the Board does not foresee the possibility of allocating sufficient
capital to continue exploration of these assets as well as investment in
production facilities, the Board has decided to write down the assets by 44,993
KSEK. The company will consider options to Joint Venture or farm-out the
project.
Outlook 2010
Construction at the Pampalo Gold Mine will continue according to schedule and
budget. Test production is expected to commence during Q4/2010 and full-scale
production during Q1/2011.
Underground development works will continue according to the project plan. The
first long-hole stope will be taken into production in September. Following
this, drifting in the waste rock and in the ore, as well as long hole stoping,
will continue. The target is to create a stockpile of approximately 3-4 months
of ore supply on the surface before start-up of full-scale production. This will
secure sufficient ore supply for production start-up, and will contribute to the
achievement of first year underground ore production targets.
Hedge program effects
The market value of the hedge programs will fluctuate in the future due to
USD/Euro exchange rates and gold price developments. The effect of the hedge
programs will be realized at term date. The company real profit will be based on
a combination of operating cost, gold production, hedge price and spot price.
The 50% hedge leaves scope to gain from the strong US Dollar price of gold and
the weak Euro, as Endomines' operating costs are in Euros and its production
sold in US Dollars.
Personnel
In the near future, Endomine's head count will increase to production level
manning as on-going training programs will be completed and the trainees will
join the Pampalo Gold Mine team.
Summary of key financial figures for January-June 2010 (2009)
* Earnings after tax -61,867 KSEK (-6,553)
* Earnings per share -0.84 SEK (-0.19)
* Investments 87,387 KSEK (7,053)
* Total Cash Flow -57,033 KSEK (-14,467)
Full interim report (in Swedish) is available at www.endomines.com.
For further information:
Markus Ekberg, CEO of Endomines AB, cell phone: +358 40 706 48 50
About Endomines
During 2009-2010 Endomines has taken several important steps to develop the
business from exploration to full-scale gold production. By the end of 2010, the
company will commence production at the Pampalo Gold Mine, with a projected
output of 900-1.000 kg of gold per annum. Other deposits along the Karelian Gold
Line will be exploited subsequently. Endomines has additional claims in Finnish
Lappland (gold), Ostrobothnia (ilmenite) and Southern Finland
(limestone/wollastonite).
Endomines applies SveMin's & FinnMin's respective rules for reporting (public
mining & exploration companies). Endomines has chosen to report mineral
resources and ore reserves according to JORC or NI 43-101-cod, which are
internationally accepted. Endomines applies International Financial Reporting
Standards (IFRS) as approved by the European Union.
The shares of Endomines AB are quoted on the First North Premier segment in
Stockholm under ticker ENDO.ST. Erik Penser Bankaktiebolag acts as Certified
Adviser and Liquidity Provider.
Read more about Endomines on www.endomines.com
[HUG#1438128]
Summary of Interim Report Q2 2010:
http://hugin.info/138043/R/1438128/382746.pdf
This announcement is distributed by Thomson Reuters on behalf of
Thomson Reuters clients. The owner of this announcement warrants that:
(i) the releases contained herein are protected by copyright and
other applicable laws; and
(ii) they are solely responsible for the content, accuracy and
originality of the information contained therein.
All reproduction for further distribution is prohibited.
Source: Endomines AB via Thomson Reuters ONE
Unternehmensinformation / Kurzprofil:
Bereitgestellt von Benutzer: hugin
Datum: 16.08.2010 - 12:14 Uhr
Sprache: Deutsch
News-ID 39708
Anzahl Zeichen: 0
contact information:
Town:
Stockholm
Kategorie:
Business News
Diese Pressemitteilung wurde bisher 185 mal aufgerufen.
Die Pressemitteilung mit dem Titel:
"Endomines AB Press Release, Summary of interim report January - June 2010"
steht unter der journalistisch-redaktionellen Verantwortung von
Endomines AB (Nachricht senden)
Beachten Sie bitte die weiteren Informationen zum Haftungsauschluß (gemäß TMG - TeleMedianGesetz) und dem Datenschutz (gemäß der DSGVO).





