East Africa Metals provides update on on-going project advancement

East Africa Metals provides update on on-going project advancement

ID: 483005

(firmenpresse) -

East Africa Metals provides update on on-going project advancement

Vancouver, British Columbia - July 13, 2016 - East Africa Metals Inc. (TSX-V: EAM) (East Africa or the Company) is pleased to report on an anticipated active Fall 2016 program on the development and exploration fronts, as the Company looks to address corporate objectives including; the completion of mine permitting, closing of project financing, and the initiation of development for the Terakimti Gold Oxide project, the anticipated startup of operations at Magambazi in Tanzania, and continued work to grow the resource base in Ethiopia through exploration and definition drilling.

The Companys current resource base in Ethiopia comprises 926,000 gold equivalent ounces in the indicated category plus 860,000 gold equivalent ounces in the inferred category (see table below and news release dated June 29, 2016) from Terakimti, Mato Bula, and Da Tambuk mineral resources. Exploration targets that EAM plans to test, to continue the growth of the resource base, will include the VTEM09 and Mayshehagne prospects (highlight intersections previously released are listed in the table below), and new targets along the largely underexplored Mato Bula trend.

Options for geophysically assessing the entire Mato Bula trend are presently being investigated, potentially providing the most cost effective forward program to systematically develop additional gold targets at depth for drill testing. Ground geophysical testing has yet to be initiated on the property, and offers significant opportunity for further discovery.

VTEM09 and Mayshehagne Previously Released Highlight Intervals
*Hol FromTo InterCoppeGoldSilvZincLocaDip Prospec
e (m) (mval r er l t
ID ) (m)* Azi
% g/ muth
t g/t %

HD00 24.044.20.705.00 1.0331 8.2090 -61 Maysheh




2 0 70 agne

incl28.741.12.807.77 1.6250 12.6
udin5 55 6
g

HD00 62.080.18.003.23 0.9522 3.7890 -45 Maysheh
6 0 00 agne

incl62.067.5.45 7.05 1.2446 6.45
udin0 45
g

TVD0 20.230.10.213.16 3.9787 3.82271 -47 VTEM09
01 9 50

incl21.524.2.82 5.61 7.48102 0.72
udin8 40
g

TVD0 58.268.10.752.24 2.6371 3.74263 -60 VTEM09
02 0 95
*Original holes and qualifying data released March 12, 2012, August 8, 2012, July 23, 2013, and May 27, 2015. Minor variance may occur due to QAQC interval adjustments.

East Africa's Mineral Resources at Harvest and Adyabo.

Project Ownership Resource Summary
Adyabo 3(Indicate 100% 446K Ounces AuE
d) quiv

Adyabo 3(Inferred 100% 434K Ounces AuE
) quiv

Terakimti Oxide 70% (Permit 132K Ounces AuE
Update Pending) quiv

1 (Indicated)
Terakimti 70% 348K Ounces AuE 139M lbs Cu
Sulphide quiv Equiv

2 (Indicated)
Terakimti 70% 426K Ounces AuE 170M lbs Cu
Sulphide quiv Equiv

2 (Inferred)

The resources stated above have been previously disclosed in News Releases.
1Terakimti Oxide Resource update disclosed October 27, 2015; effective date October 18, 2015. Full mineral resource estimate disclosure can be found in the company's press release dated October 27, 2015, available at www.eastafricametals.com or at www.sedar.com. Subsequent to the release of the Oxide Resource update, a review by the resource QP identified an error in the tabulation of mineral resources. The corrected resource information was disclosed via press release on January 11, 2016. Metal prices for gold and silver are $1,300/oz and $17.50/oz, respectively.
2Terakimti Initial Resource Estimate as disclosed in the 43-101 Technical Report dated February 14, 2014; effective date January 17, 2014. Full mineral resource estimate disclosure can be found on the company's website or at www.sedar.com. Metal prices for gold, silver, copper, and zinc are $1,400/oz, $25.00/oz, $3.50/lb, and $0.90/lb, respectively.
3Adyabo project updated mineral resource estimate disclosed via press release dated June 14, 2016; effective date May 31, 2016. Metal prices for gold, silver, and copper are $1,400/oz, $20.00/oz, and $3.20/lb, respectively. Metallurgical recoveries of 97% for gold, 72% for copper, and 50% for silver were applied at Da Tambuk.

About East Africa

The Company's principal assets and interests include both the 70%-owned Harvest polymetallic VMS exploration Project, which hosts the Terakimti Deposit and which covers approximately 86 square kilometres in the Tigray region of Ethiopia, 600 kilometres northnorthwest of the capital city of Addis Ababa, and the Adyabo Project, hosting the Mato Bula trend Adyabo Resource, covering 225 square kilometres immediately west of the Harvest Project. The Company owns 80% of the Adyabo Project, and upon execution of a net smelter return agreement the Company will own 100% of the Adyabo Project, subject to a 2% NSR. East Africa now has mineral resources defined at both projects in Ethiopia and plans to continue to test priority targets. Additionally, the Company owns the 93 square kilometre Handeni Property located in north-eastern Tanzania. Handeni includes the Magambazi Project, a gold deposit discovered in 2009. East Africa has entered into a definitive agreement with an arm's length private exploration and development company to advance the project.

More information on the Company can be viewed at the Companys website: www.eastafricametals.com.

Jeff Heidema, P.Geo., VP Exploration, a Qualified Person under the definitions of National Instrument 43-101, has reviewed and approved the contents of this news release.

On behalf of the Board of Directors:
Andrew Lee Smith, P.Geo., CEO

For further information contact:
Nick Watters, Business Development
Telephone-+1 (604) 488-0822
Email--investors(at)eastafricametals.com
Website--www.eastafricametals.com

East Africa Metals Inc.
Suite 700 - 1055 W. Georgia StreetPO Box 11108, Vancouver, BC, Canada V6E 3P3Tel: 604.488.0822
Toll Free: 866.488.0822
Fax: 604.899.1240Web: www.eastafricametals.com

Cautionary Statement Regarding Forward-Looking Information
This news release contains "forward-looking information" within the meaning of applicable Canadian securities legislation. Generally, forward-looking information can be identified by the use of forward-looking terminology such as "anticipate", "believe", "plan", "expect", "intend", "estimate", "forecast", "project", "budget", "schedule", "may", "will", "could", "might", "should" or variations of such words or similar words or expressions. Forward-looking information is based on reasonable assumptions that have been made by East Africa as at the date of such information and is subject to known and unknown risks, uncertainties and other factors that may cause the actual results, level of activity, performance or achievements of East Africa to be materially different from those expressed or implied by such forward-looking information, including but not limited to: early exploration; the closing of the agreement with the exploration and development company to advance the Magambazi Project or identify any other corporate opportunities for the Company; mineral exploration and development; metal and mineral prices; availability of capital; accuracy of East Africa's projections and estimates, including the initial mineral resource for the Adyabo, Harvest and Magambazi Projects; estimated exploration licence extensions, interest and exchange rates; competition; stock price fluctuations; availability of drilling equipment and access; actual results of current exploration activities; government regulation; political or economic developments; foreign taxation risks; environmental risks; insurance risks; capital expenditures; operating or technical difficulties in connection with development activities; personnel relations; the speculative nature of strategic metal exploration and development including the risks of diminishing quantities of grades of reserves; contests over title to properties; and changes in project parameters as plans continue to be refined, as well as those risk factors set out in East Africas managements discussion and analysis for the year end December 31, 2015, managements discussion and analysis for the three months ended March 31, 2016 and East Africas listing application dated July 8, 2013 and Tigray Resources Inc. Management Information Circular dated March 28, 2014. Forward-looking statements are based on assumptions management believes to be reasonable, including but not limited to the successful integration of Tigray Resources Inc.s business with the Company; the price of gold, silver, copper and zinc; the demand for gold, silver, copper and zinc; the ability to carry on exploration and development activities; the timely receipt of any required approvals; the ability to obtain qualified personnel, equipment and services in a timely and cost-efficient manner; the ability to operate in a safe, efficient and effective manner; and the regulatory framework regarding environmental matters, the renewal or extension of exploration licences, and such other assumptions and factors as set out herein. Although East Africa has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking information, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that such information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such information. The Company does not update or revise forward looking information even if new information becomes available unless legislation requires the Company do so. Accordingly, readers should not place undue reliance on forward-looking information contained herein, except in accordance with applicable securities laws.

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Unternehmensinformation / Kurzprofil:
Leseranfragen:

Zu den wichtigsten Projekten und Beteiligungen des Unternehmens gehören das zu 70 % unternehmenseigene polymetallische VMS-Explorationsprojekt Harvest, das sich über eine Fläche von rund 116 Quadratkilometern in der äthiopischen Region Tigray rund 600 Kilometer nord-nordwestlich der Hauptstadt Adis Ababa erstreckt, und das Projekt Adyabo, das unmittelbar im Westen des Projekts Harvest eine Fläche von 312 Quadratkilometern einnimmt. Das Unternehmen hat eine Vereinbarung zum Erwerb einer Beteiligung von bis zu 80 % am Projekt Adyabo unterzeichnet.



Bereitgestellt von Benutzer: irw
Datum: 13.07.2016 - 09:36 Uhr
Sprache: Deutsch
News-ID 483005
Anzahl Zeichen: 11154

contact information:
Town:

Wien



Kategorie:

Business News



Diese Pressemitteilung wurde bisher 319 mal aufgerufen.


Die Pressemitteilung mit dem Titel:
"East Africa Metals provides update on on-going project advancement
"
steht unter der journalistisch-redaktionellen Verantwortung von

EAST AFRICA METALS INC (Nachricht senden)

Beachten Sie bitte die weiteren Informationen zum Haftungsauschluß (gemäß TMG - TeleMedianGesetz) und dem Datenschutz (gemäß der DSGVO).


Alle Meldungen von EAST AFRICA METALS INC



 

Werbung



Facebook

Sponsoren

foodir.org The food directory für Deutschland
Informationen für Feinsnacker finden Sie hier.

Firmenverzeichniss

Firmen die firmenpresse für ihre Pressearbeit erfolgreich nutzen
1 2 3 4 5 6 7 8 9 A B C D E F G H I J K L M N O P Q R S T U V W X Y Z