SeaBird - Report 2nd Quarter 2011

SeaBird - Report 2nd Quarter 2011

ID: 57346

(Thomson Reuters ONE) -


HIGHLIGHTS Q2 2011 AND SUBSEQUENT EVENTS

·       The Ocean Bottom Node ("OBN") survey with Hugin Explorer and Munin
Explorer on Rosebank west of Shetland for Chevron North Sea Ltd commenced on 20
April 2011 and the performance has been in accordance with plan. The survey was
successfully completed on 16 August.

·       A new 4C OBN survey of two-three weeks duration in the Norwegian Sea for
ExxonMobil Exploration, and Production Norway AS as the PL596 operator, was
awarded on 4 August 2011. This is a pilot survey utilising the SeaBird's OBN
technology in sub-basalt structures which are difficult to image with other
seismic methods. This is the fifth of the "supermajors" (following Total, BP,
Chevron and Shell) to utilise SeaBird's proprietary OBN technology.

·       End of May 2011 SeaBird decided to postpone the planned construction of
a second OBN vessel until a longer term backlog can be achieved for the present
OBN operation.

·       Effective on 20 May 2011, a frame agreement was entered into with
Spectrum ASA for the acquisition of 2D seismic data using SeaBird vessels to a
minimum value of USD 23 million over a period of 36 months (thereof 50% within
the first 12 months), and a re-let agreement for M/V GGS Atlantic on a bareboat
charter basis to SeaBird until August 2012.

·       Several 2D/3D contracts have been awarded during Q2 2011, continuing the
positive trend experienced in Q1 2011.

·       Following an application from SeaBird, bondholders of the NOK 81.75
million (net 78.75) bond approved in a bondholders meeting on 21 July 2011 to
postpone the maturity of the loan for two months to 14 September 2011 with a
repayment price at 104% and increased margin from 4.25% to 9.25% from 14 July
2011 to maturity.

·       In the beginning of August 2011, SeaBird entered into a three years




(plus 3x1 year options) bare-boat charter with the owners Koleth Singapore (Pte)
Ltd of the four streamer 3D vessel Voyager Explorer (built 2005). The vessel
will replace the Geo Mariner which will be de-rigged and deactivated. Contracts
previously allocated to Geo Mariner will be performed by Voyager Explorer,
keeping the vessel engaged from mid August through Q4 2011.


KEY FINANCIAL PERFORMANCE FIGURES

Revenues and expenses for Q2 2011 and Q2 2010 are difficult to compare as
several changes in the operating performance of the Ocean Bottom Node ("OBN")
activity and the utilisation of the 2D/3D fleet in these two quarters have
affected the numbers.

The OBN activity in Q2 2010 was partly on the Agbami field in Nigeria up to 20
April, then mobilisation to the North Sea for Chevron on the Rosebank 1 survey
from end May. The OBN operation in Q2 2011 started for Chevron on Rosebank 2 on
20 April after a four months idle period. Revenues for the OBN operation were
about USD 21 million in Q2 2011 compared to USD 27 million in Q2 2010. The cost
of the OBN operation was about the same in Q2 both years.

In the 2D/3D shallow water segment, the utilisation was still low in Q2 2011 at
62% compared to 76% in Q2 2010, resulting in a revenue level of USD 20 million
in Q2 2011 compared to USD 23 million in Q2 2010. Operating expenses are about
USD 2 million higher in Q2 2011 compared to Q2 2010.

Sequential development:

Consolidated revenues for the SeaBird Group was USD 44.1 million in Q2 2011, up
from USD 21.2 million in Q1 2011 and USD 37.6 million in Q4 2010. The increased
revenues are mainly due to the OBN survey commencing on Rosebank 2 from 20 April
2011, following mobilisation, while the two vessels working with OBN were idle
during most of Q1 2011.  Also revenues contribution from the 2D fleet improved
during this quarter by USD 4 million compared to the previous quarter, as more
vessels were back in operation following extensive idle periods in Q1 2011 and
Q4 2010. Multiclient sales in Q2 2011 were USD 2.9 million compared to USD 1.0
million in Q1 2011.

Operating expenses increased during Q2 2011 to USD 30.1 million from USD 23.6
million in Q1 2011. The increase refers to improved utilisation and consequently
several vessels moving from idle mode with reduced cost in Q1 2011 to full
operating cost in Q2 2011. In addition, the M/V GGS Atlantic joined the 2D fleet
from 20 May 2011 as part of the frame agreement with Spectrum.

Earnings before interest, taxes, depreciation and amortisation ("EBITDA") were
positive at USD 8.2 million in Q2 2011 against a negative EBITDA of USD 8.7
million in Q1 2011.

General and administrative ("SG&A") expenses are reduced to USD 5.9 million in
Q2 2011 compared to USD 6.3 million in Q1 2011. SG&A is continuing at the same
level at about USD 6 million as in previous quarters (excluding write off for
bad debt). The higher costs in Q1 2011 were mainly due to additional legal cost
for debt refinancing.

Depreciation and amortisation is USD 12.2 million in Q2 2011 compared to USD
11.9 million in Q1 2011. This is mainly due to higher amortisation of
Multiclient library in Q2 2011.

An impairment adjustment for Geo Mariner will be recorded in Q3 2011 when the
potential sales value of the vessel and values of various seismic and other
equipment moved to Voyager Explorer and other SeaBird vessels are clarified.

Interest expense is up by about USD 2.4 million in Q2 2011 to USD 6.0 million,
mainly due to the interest of 9% on the convertible loan in favour of PGS from
22 February 2011 and increased margin on bank loans as a result of extended
maturity from 16 March 2011.

Other financial expenses of USD 4.0 million refer mainly to unrealised currency
exchange losses of USD 2.0 million on the two NOK based bond loans totalling NOK
481.75 million and restructuring fee of USD 1.2 million for extending maturity
on the bank debt.

Income tax of USD 2.6 million in Q2 2011 refers to withholding taxes and
estimated corporate taxes related to operation in various jurisdictions.

In Q2 2011 net loss after tax was USD 16.6 million compared to a loss in Q1
2011 of USD 33.2 million and a profit in Q2 2010 of USD 1.5 million.

Capital expenditures were USD 7.0 million in Q2 2011 compared to USD 1.2 million
in Q1 2011. Major capital cost items refer to the 60 new nodes for Hugin
Explorer and classification cost for this vessel.

A weakening of USD against NOK and EUR has in general a negative impact on the
operating expenses, interest expenses and gross debt as SeaBird has significant
costs in other currencies than USD and bond loans of a total of NOK 478 million.

OPERATIONAL HIGHLIGHTS

The vessel utilisation for all vessels operated by SeaBird for Q2 2011 was 69%,
up from 49% in Q1 2011.

The OBN operation with Hugin Explorer deploying and retrieving nodes and Munin
Explorer as source vessel mobilised for the Rosebank 2 survey west of Shetland
for Chevron North Sea Limited in March-April 2011. The operation commenced on
20 April 2011 following classification work at a Danish yard during this
mobilisation period.  The utilisation for the two vessels was 88% in Q2 2011,
compared to 23% in Q1 2011. A new 4C OBN contract of approximately two to three
weeks duration in the Norwegian Sea for ExxonMobil Exploration and Production
Norway AS as the PL596 operator was awarded on 4 August 2011. This is a pilot
survey utilising the SeaBird's NODE technology in sub-basalt structures which
are difficult to image with other seismic methods. Management is actively
pursuing further work, and see several opportunities coming up for various OBN
surveys through 2(nd) half of 2011 and into 2012 through bids and tenders
already submitted.

Utilisation for the 2D/3D vessels was 62% in Q2 2011 (Q1 2011:57%). The
utilisation has continued to improve during the first 6 months of 2011 from only
three vessels on contract at the beginning of the year to all 2D vessels
generating revenues or being committed to contracts at the end of Q2 2011.

Aquila Explorer had 89% utilisation in Q2 2011, and is employed to
September/October 2011. Harrier Explorer achieved 99% utilisation in Q2 2011 and
continues working under a long term charter to PGS until end September 2011,
when the vessel will go into yard for classification work. Northern Explorer had
78% utilisation in Q2 2011, and isin mobilisation/standby mode since 7 August
awaiting contract. Hawk Explorer had 56% utilisation in Q2 2011, mainly due to
classification in May/June 2011 and will be employed till end of September
2011, however further employment on a longer term 2D contract is in the process
of being concluded. For Osprey Explorer, a 50% utilisation has been allocated
during her 3 month standby in Q2 2011 while waiting on Mexican authority
approval, which was granted early August 2011. The MultiClient provider has
accepted this waiting time as cost in relation to profit sharing of MC sales. In
addition, the vessel is committed on a 2D survey in South America to end
December 2011. The M/V GGS Atlantic joined the SeaBird fleet on 21 May 2011 (not
included in statistics above) as part of the frame agreement entered into with
Spectrum ASA, and is continuing on her MultiClient work in the Barents Sea until
mid October 2011.

2D and 3D contracts have also been awarded to the Geo Mariner in Q2 2011. These
contracts will now be transferred to Voyager Explorer following the bare boat
chartering of this 2005 built 3D four streamer vessel in early August 2011.

As for the tendering and potential on the 2D and 3D market, SeaBird is satisfied
with the increased tender activity and expects several awards going forward with
the potential of improved utilisation for this segment.

LIQUIDITY AND FINANCING

At 30 June 2011, cash and cash equivalents amounted to USD 4.8 million, down
from USD 11.4 million end of March 2011.

SeaBird carried out a substantial reconstruction of its debt to strengthen the
financial position during Q1 2011 through issuing a USD 42.9 million convertible
loan with PGS. Maturity of the NOK 400 million unsecured bond was extended from
February 2012 to February 2014. Finally the maturity of the loan, presently USD
39.9 million, with a bank consortium with BN Bank (now Sparebank 1 SMN) as agent
was extended by two years to September 2014.

Following an application from SeaBird, bondholders approved in a meeting on 21
July 2011 to postpone the maturity of the USD 81.75 (net 78.75) loan for two
months to 14 September 2011, with a repayment price at 104% and increased margin
from 4.25% to 9.25% from 14 July 2011 to maturity.

Net cash flow from operating activities was USD 1.1 million for Q2 2011, against
negative USD 35.3 million for Q1 2011, and positive USD 4.2 million for Q2 2010.

During Q1 2011 instalments of USD 7.3 million were paid to banks and USD 0.7
million on the lease of Hawk Explorer. Net debt and borrowings increased to USD
208.6 million end of Q2 2011 from USD 201.41 million end of Q1 2011.

There are no further significant committed investments, except normal
maintenance type expenditures and certain equipment upgrades for our present
fleet of vessels. The Management and the Board of Directors have also decided to
put the previously planned expansion of the Ocean Bottom Node operation through
constructing a second OBN vessel on hold until a longer term contractual
prospective can be achieved.

SeaBird did not meet covenants under the Loan Agreements with banks as of 30
June 2011.  Waivers have been filed and a positive dialogue has started. SeaBird
expects a clarification shortly.

OUTLOOK

Oil prices continue at a good level, but still subject to fluctuations, and
forecasts for the future remain high. This will develop into market
opportunities for frontier exploration. However SeaBird is still very dependent
on the speed that oil companies and National Oil Companies ("NOC's") can and
will work to in regard to schedules for tenders and awards.

The 2D fleet is continuing under short contract employments, and SeaBird has a
good track record on contract utilization. Source vessel requirements are
becoming more regular as the Gulf of Mexico opens up end this year and through
to 2012.

SeaBird is moving into the 3D four to six streamer market with the entry of the
Voyager Explorer, and this already has shown benefits with the vessel fixed to
February 2012, and prospects are good for continuing utilization in the Asia-
Pacific region.

SeaBird continues to see high interest in SeaBird OBN technology with tenders
and quotations requested for high level OBN reservoir monitoring surveys and
pilot studies for new areas. The OBN market is still immature, but the four
component (4C) data now having reached completion of processing and results seen
by oil companies, SeaBird has every expectation of the market maturing through
2012 and beyond. The medium and long term future is linked to the time lapse
surveys (4D) for which SeaBird now sees the first tenders being released.
SeaBird has now reached five of the six supermajors with this technology, as
well as the NOC's behind some of the geographical survey areas, and SeaBird see
very positive responses.

SeaBird is continuing to work together with PGS to develop the areas of co-
operation for the rest of 2011 where we also see the beginnings of a demand in
Multi-Streamer and OBN surveys and the development of the offers in
combination.  This will take time to mature and is a plan for PGS for 2012 and
beyond. SeaBird will continue to market node only surveys worldwide as usual.

GUIDING OF EBITDA

SeaBird would like to revert to the EBITDA guiding for the remainder of the year
as soon as OBN contract coverage during Q3 and Q4 2011 is clarified.


The Board of Directors and Chief Executive Officer

SeaBird Exploration PLC

18 August 2011



This information is subject of the disclosure requirements pursuant to section
5-12 of the Norwegian Securities Trading Act.



Second Quarter 2011 Report:
http://hugin.info/136336/R/1539207/470312.pdf

Presentation 2nd Quarter 2011:
http://hugin.info/136336/R/1539207/470315.pdf




This announcement is distributed by Thomson Reuters on behalf of
Thomson Reuters clients. The owner of this announcement warrants that:
(i) the releases contained herein are protected by copyright and
other applicable laws; and
(ii) they are solely responsible for the content, accuracy and
originality of the information contained therein.

Source: SeaBird Exploration Ltd. via Thomson Reuters ONE

[HUG#1539207]


Weitere Infos zu dieser Pressemeldung:
Unternehmensinformation / Kurzprofil:
drucken  als PDF  an Freund senden  Evotec Receives Pre-clinical  Milestone Payment as Part of its Discovery Alliance with Boehringer Ingelheim SBM OFFSHORE N.V. HALF-YEAR RESULTS 2011 SOLID UNDERLYING RESULTS DESPITE IMPAIRMENT CHARGES
Bereitgestellt von Benutzer: hugin
Datum: 18.08.2011 - 07:30 Uhr
Sprache: Deutsch
News-ID 57346
Anzahl Zeichen: 16175

contact information:
Town:

Oslo



Kategorie:

Business News



Diese Pressemitteilung wurde bisher 189 mal aufgerufen.


Die Pressemitteilung mit dem Titel:
"SeaBird - Report 2nd Quarter 2011"
steht unter der journalistisch-redaktionellen Verantwortung von

SeaBird Exploration Ltd. (Nachricht senden)

Beachten Sie bitte die weiteren Informationen zum Haftungsauschluß (gemäß TMG - TeleMedianGesetz) und dem Datenschutz (gemäß der DSGVO).

SeaBird - Helicopter incident on Kondor Explorer ...

11 December, 2009. Cyprus: SeaBird Exploration Limited informs that an oncoming helicopter to the Kondor Explorer made a controlled emergency landing on water at about 1210 hours CET today a few hundred meters away from the vessel on the Agbami fie ...

Alle Meldungen von SeaBird Exploration Ltd.



 

Werbung



Sponsoren

foodir.org The food directory für Deutschland
News zu Snacks finden Sie auf Snackeo.
Informationen für Feinsnacker finden Sie hier.

Firmenverzeichniss

Firmen die firmenpresse für ihre Pressearbeit erfolgreich nutzen
1 2 3 4 5 6 7 8 9 A B C D E F G H I J K L M N O P Q R S T U V W X Y Z