First impoundment: Tamakoshi reservoir secures power supplies in Nepal

First impoundment: Tamakoshi reservoir secures power supplies in Nepal

ID: 615795

Implementation of Nepal’s largest hydropower project is approaching the finishing line: in March 2020 the Upper Tamakoshi reservoir was filled for the first time. Once regular operation of the plant commences, it will increase the country’s electricity generation capacity by around sixty percent. The joint venture between Tractebel Germany and Norconsult AS has been responsible for the detailed planning and construction management of the project since 2011.

Upper Tamakoshi hydropower project, Nepal Upper Tamakoshi hydropower project, Nepal

(firmenpresse) - Implementation of Nepal’s largest hydropower project is approaching the finishing line: in March 2020 the Upper Tamakoshi reservoir was filled for the first time. Once regular operation of the plant commences, it will increase the country’s electricity generation capacity by around sixty percent, thereby eliminating current shortfalls in the power supply system. The joint venture between Tractebel Germany (formerly Lahmeyer International) and Norconsult AS has been responsible for the detailed planning and construction management of the project since 2011.

The plant is located in a remote region of the upper Himalayas, in the Tamakoshi river basin, about six kilometres from the border with Tibet. Featuring six underground turbine units, it is expected to generate 2.3 TWh of urgently needed electricity – the project is therefore a high national priority.

Despite the difficult terrain and the major damage to the construction sites caused by the severe earthquake of 2015, 99 percent of the work has now been completed. Even under these difficult circumstances the project team has rigorously followed its objective of meeting completion deadlines. One key milestone was successfully accomplished in March 2020 when the reservoir, with a storage capacity of 1.2 million m3, was filled with water for the first time. This means that the dam and its appurtenant structures for the 456 MW peak load hydropower plant are now ready for the required technical tests.

Testing dam operation

Following the seven-day impoundment phase, power plant specialists commenced the testing programme in order to evaluate and confirm the dam functionality along with its auxiliary structures. The tests will determine whether structures comply with their design standards, assure the dam’s functionality, and verify the reliable operation of the sedimentation basins and the various mechanical equipment items. As a consequence of the current Covid-19 pandemic, and in order to ensure the health and safety of the people working on site, test activities are currently proceeding at a relatively slower pace.





Once the tests are successfully concluded, the reservoir will be emptied again to allow any rectification works to be carried out. “We hope that we will soon be able to resume our work with maximum efficiency, so that we can achieve our Project objectives as quickly as possible and deliver a Project of such importance to the Nepalese people and for the economic development of the country,” says Renos Christakis, senior geologist at Tractebel.


Themen in dieser Pressemitteilung:


Unternehmensinformation / Kurzprofil:

About Tractebel
At the helm of the Energy Transition, Tractebel provides a full range of engineering and advisory services throughout the life cycle of its clients’ projects, including design and project management.
As one of the world’s leading engineering and advisory companies and with more than 150 years of experience, it's our mission to actively shape the world of tomorrow. With about 5,000 experts and presence in more than 70 countries, we are able to offer our customers multidisciplinary solutions in energy, water and urban.



Leseranfragen:

Contact
Tractebel Engineering GmbH
Sabine Wulf, Head of Marketing Communications & CSR
Friedberger Straße 173
D-61118 Bad Vilbel

Phone: +49 (61 01) 55 - 0
info-de(at)tractebel.engie.com



drucken  als PDF  an Freund senden  Solid Oxide Fuel Cell Market 2020: Historical Analysis, Opportunities, COVID – 19 Outbreak, Latest Innovations and Top Players by 2023 Gas Generator Market 2020: Historical Analysis, Opportunities, COVID – 19 Outbreak, Latest Innovations and Top Players by 2023
Bereitgestellt von Benutzer: Lahmeyer_SEO
Datum: 02.07.2020 - 16:10 Uhr
Sprache: Deutsch
News-ID 615795
Anzahl Zeichen: 3093

contact information:
Contact person: Sabine Wulf
Town:

Bad Vilbel


Phone: +49 6101 55-0

Kategorie:

Energy & Utilities


Typ of Press Release: Company
type of sending: _CSF_VART3

Diese Pressemitteilung wurde bisher 230 mal aufgerufen.


Die Pressemitteilung mit dem Titel:
"First impoundment: Tamakoshi reservoir secures power supplies in Nepal"
steht unter der journalistisch-redaktionellen Verantwortung von

Tractebel Engineering GmbH (Nachricht senden)

Beachten Sie bitte die weiteren Informationen zum Haftungsauschluß (gemäß TMG - TeleMedianGesetz) und dem Datenschutz (gemäß der DSGVO).

Tractebel reaches 2022 emissions target ...

To contribute to global net-zero goals, in 2021 Tractebel set in motion a robust plan to reduce its carbon emissions by 20% and to neutralize its residual emissions by the end of 2022. We have now completed a comprehensive company carbon assessment f ...

Tractebel ranked top hydro plant design firm in the world ...

Tractebel is the world’s leading hydro plant design firm, according to the prestigious American magazine Engineering News-Record’s (ENR) latest ranking. The top spot is testimonial to our commitment to engineering a carbon-neutral future, and cem ...

Alle Meldungen von Tractebel Engineering GmbH



 

Werbung



Facebook

Sponsoren

foodir.org The food directory für Deutschland
Informationen für Feinsnacker finden Sie hier.

Firmenverzeichniss

Firmen die firmenpresse für ihre Pressearbeit erfolgreich nutzen
1 2 3 4 5 6 7 8 9 A B C D E F G H I J K L M N O P Q R S T U V W X Y Z